15 conditions of contract Flashcards

1
Q

What is contained in the conditions of the contract?

A

all clauses relating to the respective rights and obligations of the parties of the contract - mainly administrative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where are the technical matters of the contract?

A

the specification and drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who has ultimate responsibility for al the enquiry documents?

A

PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can be done to stop an incompetent engineer from preparing legal documents?

A

hire a specialised team to prepare conditions of the contract, often requirements for tendering, sometimes invite and receive tenders and help evaluate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are ‘general form of contract’?

A

contracts prepared and published by professional organisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can project specific provisions be added to the general form of contract?

A

annexure attached to general form and supplementary conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the fundamental requirements of general conditions of contract?

A

1 presentation- it should be easy to follow
2 equitability - no bias
3 the project manager acts as an administrator of the contract, impartial decision maker and principles rep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 4 areas of the contract that the principle and contractor often fight about?

A

1 commencement and completion
2 retention
3 defects liability
4 liquidated damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the date for substantial completion?

A

date nominated in the contract for the works to be handed over to the principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the date of substantial completion?

A

the date certified by the PM as the actual date for works being handed over to principle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 3 ways a tenderer can specify a date for commencement and completion?

A

1 nominate in tender a period for substantial completion
2 nominate in tender a date for substantial completion based on be awarded contract before a certain date
3 confirm in their tenders they can reach substantial completion by a certain date stated in tender enquiry docs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is retention?

A

portion of the payment held back by principle as guarantee that the work will be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When the the retention paid back?

A

1/2 a set period after date of substantial completion and 1/2 after the defects liability period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the defects liability period?

A

a time period where the contractor has to rectify any omissions or defects in the work- any of these are breaches of the contract so the contractor will not be paid to correct. There as different values for separate sections of work in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is the defects liability period measured?

A

1 set period of time

2 of throughput if a processing unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are liquidated damages?

A

if the contractor does not complete the work by the agreed date then will need to pay amount the principle lateness would cost.
Not a penalty.
It is pre-agreed in the contract

17
Q

What is a corollary to liquid damages?

A

a bonus for completing the work early- the amount more the principle will earn for early completion .

18
Q

How is the value for the liquidated damages evaluated?

A

1 interest payments on funds borrowed to finance project
2 cost income from non operations of the project
3 damages or costs of principle not being able to honour commitments