12 types of engineering contracts Flashcards

1
Q

What is the difference between a main and sub contract?

A

main contract between principle and main contractor, subcontract between main contractor and subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 3 common classifications for deciding the type of contract?

A

1 the method by which the contractor is selected
2 the method by which payment for the work under the contract is evaluated
3 the method by which responsibility for the technical and administrative aspects of the work is allocated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 2 routes the principle can use when selecting a contractor?

A

1 competitive tendering

2 negotiated contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 2 basis used for payment of work?

A

1 price based

2 cost based

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 2 methods of price based work payment? and explain

A

1 lump sum - stipulated price contract- can be increased or decreased if there is change in the work scope
2 measure and value- pre-agreed unit rates, schedule of rates or priced BoQ needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 2 methods of cost based work payment? and explain

A

1 cost reimbursements - plus a fee

2 target cost- adjusted for any major changes in scope- any profit shared between principle and contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the 4 methods used to evaluate the cost reimbursement fee to contractor?

A

1 fixed sum
2 fixed sum with profit sharing or bonus
3 fixed fee with sliding- scale adjustment
4 % of costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the implications of cost reimbursement payment?

A

1 allows early contractor involvement with low design level
2 final price depend on risk
3 efficiency of contractor affect cost to promoter
4 low financial charges
5 allow promoter involvement in project management
6 allows contractor to input to design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key responsibilities that must be outlined in the contract?

A
1 project management and coordination 
2 engineering design: conceptual, process, detailed, documentation 
3 procurement and supervision 
4 construction and supply/ installation
5 contract administration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the different types of contracts?

A
1 separate design and construction 
2 design and construction 
3 construction supply/ installation 
4 management 
5 construction management 
6 design and management 
7 turnkey
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the implications of separate design and construction contract?

A
1 widespread use
2 experienced designers can be selected 
3 normally used with measure and value 
4 design usually completed before tender 
5 management divided between parties 
6 can lead to disputes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does the promoter need to do for a design and construction contract?

A

appoint an engineer to provide scope of project through outline designs, design criteria, performance requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the contractors responsibility in the construction supply/ installation contract?

A

to carry out the work under the contract in accordance with design, specifications and other details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who is a appointed in a management contract and what do they do?

A

a management contractor to manage the design, construction phases and contribute to the design itself

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the implications of a management contract?

A

1 payment of management contractor is by fee, some times plus reimbursable costs
2 promoter pays contractor through management contractor
3 construction usually broken down into small packages with designs complete with high competition tender
4 designers must make more decisions early in design
5 promoter carries more risk- offset by high level of management control
6 some management contractors carry normal construction risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a construction management contract?

A

the contract is directly between contractor and principle

17
Q

What are the differences between a management and construction management contract?

A

1 construction management firm does not need to e a construction contractor
2 construction contracts have normal risk by promoter
3 construction management firm has no commercial professional conflicts of interest
4 construction manager is treated as a professional service provider + paid fee

18
Q

What is a design and management contract?

A

they have responsibility for the detailed design

19
Q

What are the similarities of a design and management contract and a management contract?

A

1 single point of contact for promoter
2 management of design and construction integrated
3 specifications must be defined early in design phase
4 time saved from design/ construction overlaps
5 likelihood of better design buildability

20
Q

What are the contractors responsibilities in a turkey contract?

A

detailed design, procurement and construction- scope of design provided by separate designer

21
Q

What are points to consider of a turkey contract?

A

1 payment may be staged lump sums or BoQ
2 full specification needed early in design stage
3 post contract promoters negotiating position is weak
4 pay need to cover cost of design by contractor in tender stage
5 checking the contractors work is likely to lead to disputes
6 promoters commissioning requirements must be in contract

22
Q

What are the requirements for a simple contract?

A
1 intention 
2 genuine consent 
3 legality of purpose 
4 legal capacity 
5 offer and acceptance
6 valuable consideration
23
Q

Give an example of when a lumpsum price based contract was used

A

the millennium stadium in wales

24
Q

Give an example of when a target cost based contract was used

A

The queens ferry crossing

25
Q

Give an example of when earned measure and value based contract was used

A

for building roads in north Lanarkshire

26
Q

Give an example of when cost reimbursement based contract was used

A

holyrood parliament