12 types of engineering contracts Flashcards
What is the difference between a main and sub contract?
main contract between principle and main contractor, subcontract between main contractor and subcontractor
What are the 3 common classifications for deciding the type of contract?
1 the method by which the contractor is selected
2 the method by which payment for the work under the contract is evaluated
3 the method by which responsibility for the technical and administrative aspects of the work is allocated
What are the 2 routes the principle can use when selecting a contractor?
1 competitive tendering
2 negotiated contract
What are the 2 basis used for payment of work?
1 price based
2 cost based
What are the 2 methods of price based work payment? and explain
1 lump sum - stipulated price contract- can be increased or decreased if there is change in the work scope
2 measure and value- pre-agreed unit rates, schedule of rates or priced BoQ needed
What are the 2 methods of cost based work payment? and explain
1 cost reimbursements - plus a fee
2 target cost- adjusted for any major changes in scope- any profit shared between principle and contractor
what are the 4 methods used to evaluate the cost reimbursement fee to contractor?
1 fixed sum
2 fixed sum with profit sharing or bonus
3 fixed fee with sliding- scale adjustment
4 % of costs
What are the implications of cost reimbursement payment?
1 allows early contractor involvement with low design level
2 final price depend on risk
3 efficiency of contractor affect cost to promoter
4 low financial charges
5 allow promoter involvement in project management
6 allows contractor to input to design
What are the key responsibilities that must be outlined in the contract?
1 project management and coordination 2 engineering design: conceptual, process, detailed, documentation 3 procurement and supervision 4 construction and supply/ installation 5 contract administration
What are the different types of contracts?
1 separate design and construction 2 design and construction 3 construction supply/ installation 4 management 5 construction management 6 design and management 7 turnkey
What are the implications of separate design and construction contract?
1 widespread use 2 experienced designers can be selected 3 normally used with measure and value 4 design usually completed before tender 5 management divided between parties 6 can lead to disputes
What does the promoter need to do for a design and construction contract?
appoint an engineer to provide scope of project through outline designs, design criteria, performance requirements
What is the contractors responsibility in the construction supply/ installation contract?
to carry out the work under the contract in accordance with design, specifications and other details
Who is a appointed in a management contract and what do they do?
a management contractor to manage the design, construction phases and contribute to the design itself
What are the implications of a management contract?
1 payment of management contractor is by fee, some times plus reimbursable costs
2 promoter pays contractor through management contractor
3 construction usually broken down into small packages with designs complete with high competition tender
4 designers must make more decisions early in design
5 promoter carries more risk- offset by high level of management control
6 some management contractors carry normal construction risks
What is a construction management contract?
the contract is directly between contractor and principle
What are the differences between a management and construction management contract?
1 construction management firm does not need to e a construction contractor
2 construction contracts have normal risk by promoter
3 construction management firm has no commercial professional conflicts of interest
4 construction manager is treated as a professional service provider + paid fee
What is a design and management contract?
they have responsibility for the detailed design
What are the similarities of a design and management contract and a management contract?
1 single point of contact for promoter
2 management of design and construction integrated
3 specifications must be defined early in design phase
4 time saved from design/ construction overlaps
5 likelihood of better design buildability
What are the contractors responsibilities in a turkey contract?
detailed design, procurement and construction- scope of design provided by separate designer
What are points to consider of a turkey contract?
1 payment may be staged lump sums or BoQ
2 full specification needed early in design stage
3 post contract promoters negotiating position is weak
4 pay need to cover cost of design by contractor in tender stage
5 checking the contractors work is likely to lead to disputes
6 promoters commissioning requirements must be in contract
What are the requirements for a simple contract?
1 intention 2 genuine consent 3 legality of purpose 4 legal capacity 5 offer and acceptance 6 valuable consideration
Give an example of when a lumpsum price based contract was used
the millennium stadium in wales
Give an example of when a target cost based contract was used
The queens ferry crossing
Give an example of when earned measure and value based contract was used
for building roads in north Lanarkshire
Give an example of when cost reimbursement based contract was used
holyrood parliament