3 Parties in a project Flashcards
What are the aims of the promoter?
1 Obtain best economic solution
2 Bare safety of all those working
Environmental considerations
What are the aims of the PMT?
1 Achieve optimal solution for promoter
2 Manage and define project to ensure aims are being achieved
What are the roles of the project manager?
1 Foresee as many dangers as possible + minimise 2 Achieve project aims 3 Control costs 4 Control schedule 5 Lead team 6 Liaise with promoter 7 Liaise with contractor 8 Measure and report on progress
What are the aims and responsibilities of the designer?
1 Produce a design to achieve the promoter’s objectives 2 Feasibility studies 3 Design options 4 Necessary approvals 5 Define project stages 6 Prepare contract documents 7 Advise on contractor 8 Technically supervise construction 9 Measure, value and authorise payment
What is a nominated contractor?
promoter or designer has said only that company can carry out specific work
What are the aims of the main contractor?
1 Provide quality project 2 On time 3 On budget 4 Safely + consider environment 5 Maximise profits
What are the responsibilities of the main contractor?
1 Appoint staff + get plant and materials
2 Maybe design the works
3 Insure construction works until completion
4 Plan and programme construction
5 Design + construct temporary works
6 supervise sub-contractors
What are the different groups that could operate the finished works?
1 Separate, independent company
2 The contractor
3 The promoter
Under what circumstances would the main contractor operate after construction?
1 If they have entered a separate operation agreement with promoter
2 If it was required as part of the original contract
who designed the Scottish Parliament?
Enric Miralles, Spanish architect
what are the responsibilities of the promoter?
1 identify and be satisfied that the project will meet them
2 define nature and functions of project
3 usually operate at completion
4 usually pay
Whats the aim of the designer?
Produce a design that will achieve the promoter’s objectives, including requirements for
minimum cost and environmental sensitivity.