3.3.4. Critical Path Analysis Flashcards
CPA
Technique used to plan most time efficient way to complete complex projects. Used to:
-get product to market as quick as possible
-move offices or production to new locations
EST
Earliest start time is earliest possible date activity can begin
On top right hand corner of node before each activity
EST of 1st node is always 0.
LFT
latest possible date it must be competed to avoid delaying overall project
Float time
Float time is shack time available attached to an activity.
LFT of activity-Duration of activity- EST of activity
+ves of CPA
-Identifying activities that can be carried out simultaneously shortens overall duration of project.
-Resources needed for activity can be delivered just in time to avoid delays
-Shows ways to avoid delays by allocating extra resources etc
-Ves of CPA
-Can give managers false sense of security as it shows what can happen but to hit deadlines work must actually be competed
-Not drawing activity lines could devalue diagrams visual use.
-Diagrams for really compact projects may be unmanageably large.