Works Progress and Quality Management Flashcards
How is the design programme collated and who owns this document?
Architect collates and owns.
Who’s responsibility is it to report against a design programme?
Architect at project meetings
How regularly would you receive a dropline programme and review against it?
Weekly and reviewed weekly. Unless a project of a larger scale.
What is the difference between a contract administrator and a clerk of works?
- CA’s role is to administer the contract only.
- Clerk of works - Reviews quality, safety and workmanship.
On the Cat B fit -out 20 Fen, how did you inform your client of this significant delay?
- Received contractor dropline.
- Reviewed on site
- Understood mitigation approach.
- advised programme of delay and approach to mitigate.
Is the delay of the materials a relevant event / matter?
- Relevant event as down to factors outside of contractor control.
Why did the FCU delivery prevent the 2nd fix M&E being progressed
- FCU being installed.
- Pipework being connected to FCU.
Did the fan coil unit delivery delay have an impact on any other elements of works?
Ceiling being installed.
What was your involvement during this programme re-sequencing?
- Regular meetings with contractor
- Review of re-sequencing options to ensure realistic.
What items were you looking for when ensuring the re-sequenced programme was realistic?
- Stacking of works
- Ensure realistic chain of works
- Reviewing to ensure the approach looked safe.
Aside from the programme dropline did you use any other indicators to review progress on site?
- Site reviews
- Cash flow
- Procurement schedule.
What programme risks would you identify to your client?
- Deliveries
- Logistics / goods lift
- Noisy works.
Who would typically be the owner of the design programme on your projects?
- The lead designer (architect) would.
- This would be factored into my master programme.
How long was the FCU delivery delayed?
- 2 weeks.
Why was the programme re-sequenced once the materials were received? Should this not have been done earlier?
- It was re-sequenced prior to mitigate delay and understand drop dead date for when FCU’s were required before delay to PC.
- Once received to site then a full re-sequence took place to ensure accurate contractor reporting.