Project Finance Flashcards
What is the difference between value engineering and value management?
Value engineering - Retrospective
Value Management - Proactive.
How would typically control cost through a project?
- Appoint QS.
- Proactive value management approach
- Regular reporting
How do cost estimates assist with the control of cost through a project?
- Provide an estimate of cost at key junctures
- Allow client to understand cost against budget
- Allow for further decisions to be contextualised against estimate and budget.
What are preliminaries?
Costs that are essential for the completion of a project, but aren’t reflected in the finished build
Could you please provide an example of preliminary costs?
- Temporary lighting
- Labour cost
- Site insurance
- Welfare
What is overheads and profit?
- Cost for contractor to make profit and pay bills.
What is typically the OH&P percentage on jobs you are involved with?
- 3 - 7.5%
Who typically manages the professional team fees for the projects you are involved with?
Project Manager
What is the current cost of construction inflation?
4.2% as of June 2023.
What is a cashflow forecast?
- Table
-Shows expected valuation amounts for the project. - Generally calculated monthly.
What shape is a cashflow forecast for a fit-out project
- S graph
What is the shape of a cash flow forecast for a Cat A Refurb?
- Bell curve.
What are some key elements of the RICS cost reporting guidance note?
- Purpose of cost reporting
- Treatment of variations
- Risk allowance management
What is contingency?
A sum held within a clients budget to pay for any discoverable / change when on site.
What percentage contingency do you typically have on a project?
Changes through the deign stages but typically 7.5%