Programming and Planning Flashcards
How would you go about accelerating works?
Acceleration clause within the JCT contract, contractor has 7 days to provide a quotation.
What would you expect to see on an acceleration quotation?
- Cost for acceleration
- Method for acceleration
- Revised programme for acceleration.
What are methods that would be reviewed to achieve acceleration or delay mitigation?
- Out of hours working
- Additional labour
- different working practices (crane lifts?)
What are the different types of programme dropline
- Jagged.
- Straight
What are the different types of programme float?
- Total float - the amount of time a scheduled activity can be delayed without delaying the overall project completion date.
- Free Float - the amount of time that a task can be delayed without affecting the start date of its subsequent tasks
What is programme float?
Contingency within a programme to account for any delays.
What is the relationship between float and critical path?
- Float allows for tasks to be delayed before impacting critical path.
- If all float used then direct tasks will impact critical path.
What would you review prior to requesting an acceleration quote?
- Programme re-sequence
How do you go about compiling a programme?
- Consult with project team on design stages / tender duration.
- Input each task and associated milestones .
- Determine critical path
- Account for any key dates for the client which may determine procurement strategy.
How do you use a programme in the project manage?
- Key upcoming milestones
- Reporting tool for client w/ dropline
- Project team report against progress.
Could you please outline some pre contract milestones?
- Professional team appointment
- End of RIBA design stages
- Tender issue.
- Tender return
- Contractor Interviews.
Could you please outline some key post-contract milestones?
- Start on site date
- Sectional completions
- Practical Completion
- Long lead in procurement dates.
Aside from Project commander, are you aware of any other programming software?
Microsoft Project
Aside from a dropline, how else could you report on programme progress to a client?
- Percentage complete
- RAG status
Why is reviewing cash flow against programme important?
- Contractor cash flow lower than expected.
- Provides indication of programme delay.
- Trigger me to review programme on site.
What scope is typically included within a Cat A refurbishment?
- RAF
- Ceiling
- Lighting
- M&E refurb
On the King william street project, why did your client have concerns over programme duration?
- No rental income on the floor.
- Disturbance to surrounding tenants.
How did your programme provide comfort on your clients programme duration concerns?
- Demonstrated efficiency
- Allowed them to factor durations into viability calculations
How do you ensure adequate construction periods within your programme?
- Benchmarking
- Understanding of lead in periods
- Assess scale / complexity
Are client approvals a programme risk? How do you factor this in within your programmes?
Yes:
- a week period allowed for at the end of each design stage.
- Close dialogue with client to ensure aware of timely approvals and project design.
On Cat A King William Street, How did you go about presenting the programme to your client?
- Presented to client during meeting.
- Explained logic of key dates
What is a programme dropline?
- Progress line on the programme against a reporting date.
- Shows progress against each “live” bar.
- Progress based on actual against expected.
What do you typically include on a dashboard report?
- Key contract dates.
- Key client decisions required.
- Progress update over previous period.
- Key risks.
What would you do if a contractor was tracking behind programme?
- Review dropline against progress on site.
- Review contractors approach to mitigate and ensure valid.
- Report back to client on delay and approach to mitigate.