Theme 3 Topic 9 - Critical Path Analysis Flashcards
Define Critical Path Analysis
Using a network diagram to show the tasks taken to complete a project in the minimum time possible
What does a critical path analysis show?
The sequence of activities required for the project and the order in which they can be completed
What is the purpose of a critical path analysis?
To plan projects in a way which enables a project to be completed in the shortest time possible
What three things does a manager need to know to use the technique?
What different tasks are involved, The length of time each task is expected to take, The order the tasks must be completed in
Define Node
Circles representing a point in time at the start or end of an activity, They are split into three
Define Earliest Start Time (EST)
The top right segment of the node showing the earliest time an activity can begin
What does the EST depend on?
The completion of the previous activity
Define Latest Finishing Time (LST)
The bottom right segment of the node showing the latest time an activity can finish without delaying the overall project
Define Node Numbers
The left half of the node showing a unique identity for each node
What do the arrows/lines represent?
Production activities
Which way must arrows/lines go and what should they have at each end?
Left to right and must begin and end with a node
What is above the arrows/lines?
A letter or description of the activity that the line represents
What is below the arrows/lines?
A number which represents the length of time it takes to complete that activity
Define Critical Path
The sequence of activities in a project that must be completed within a designated time in order to prevent any delay in overall completion of the project
What symbol is used to show the critical path?
//