SCOPE 3 Flashcards
Project manager must reconcile the scope to the ____ and ____, as well as to the other ____ ____, to resolve any issues before work begins.
SCHEDULE AND BUDGET, PROJECT CONSTRAINS
Whether a project uses a plan-driven or change-driven approach, the process of Define Scope is _____ as the project progresses.
ITERATED
What are the inputs of Define Scope process?
PROJECT CHARTER, PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS, EEF’s, OPA’s
What are the Define Scope T&T’s?
EXPERT JUDGEMENT, DATA ANALYSIS, DECISION MAKING, INTERPERSONAL AND TEAM SKILLS, PRODUCT ANALYSIS
Product analysis technique is performed to analyze the _____ and _____ of the product as stated by customer or sponsor, which is then used to define ____ _____.
OBJECTIVES AND DESCRIPTION; TANGIBLE DELIVERABLES
Project Manager may need to determine and define _____ as part of the project, rather than receiving a complete list from the _____.
DELIVERABLES, CUSTOMER
What are the Define Scope process outputs?
PROJECT SCOPE STATEMENT, PROJECTS DOCUMENTS UPDATES
What is the primary result of the Define Scope process?
PROJECT SCOPE STATEMENT
One way to avoid project scope misunderstanding is to identify in the project scope statement what ____ in the project, to make it clear that such additions are not allowed.
IS NOT
The project scope statement, along with the WBS and WBS dictionary comprise the ____ _____., which is a part of the project management plan.
SCOPE BASELINE
The project scope statement may include the following:
PRODUCT SCOPE, PROJECT SCOPE, DELIVERABLES OF THE PROJECT, ACCEPTANCE CRITERIA, WHAT IS NOT PART OF PROJECT, ASSUMPTIONS AND CONSTRAINS
Process of subdividing project deliverables and project work into smaller, more manageable components.
Create WBS Process
The key benefit of Create WBS process is that it provides a framework of what has to be ____.
DELIVERED
Create WBS process is performed ____ or at ____ ____ in the project.
ONCE, PREDEFINED POINTS
The WBS is a hierarchical decomposition of the total ____ ____ to be carried out by the project team to accomplish the project ____ and create the required ____.
SCOPE OF WORK, OBJECTIVES, DELIVERABLES