When possible, the detailed project schedule should remain ____ throughout the project to ____ for knowledge gained, increased understanding of the risk, and value-added activities.
FLEXIBLE; ADJUST
Adaptive planning defines a ___ but acknowledges that once work starts, the priorities may ____ and the plan needs to ____ this new knowledge.
PLAN; CHANGE; REFLECT
A technique used for constructing a schedule model in which activities are presented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
PRECEDENCE DIAGRAM METHOD - PDM
CPM
CRITICAL PATH METHOD
WIP
WORK-IN-PROGRESS
Name 4 techniques CPM may use
Critical chain, rolling wave planning, program evaluation and review techniques (PERT), and integrated master scheduling (IMS).
Examples of high-uncertainty work includes ___ ___ and ___ ____.
SOFTWARE ENGINEERING’ PRODUCT DESIGN
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
PLAN SCHEDULE MANAGEMENT PROCESS
The key benefit of Plan Schedule Management process is that it provides ___ and ___ on how the project schedule will be managed ____ the project. This process performed ___ in the project
GUIDANCE AND DIRECTION; THROUGHOUT; once
What are the Plan Schedule Management process inputs?
PROJECT CHARTER; PROJECT MANAGEMENT PLAN; EEF’s; OPA’s
What are the components of the Plan Schedule Management project management plan?
SCOPE MANAGEMENT PLAN; DEVELOPMENT APPROACH
What are the Plan Schedule Management T&T’s?
EXPERT JUDGEMENT; DATA ANALYSIS; MEETINGS
What are the Plan Schedule Management outputs?
SCHEDULE MANAGEMENT PLAN
Process of identifying and documenting specific actions to be performed to produce the project deliverables.
DEFINE ACTIVITIES PROCESS
The key benefit of Define Activities process is that it decomposes ____ ____ into ____ ____ that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
WORK PACKAGES; SCHEDULE ACTIVITIES