SCHEDULE 2 Flashcards

1
Q

The process of identifying and documenting relationships among the project activities.

A

SEQUENCE ACTIVITIES PROCESS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The key benefit of Sequence Activities process is that it defines logical ____ of work to obtain the greatest ____ given all project ____. This process is performed ___ the project.

A

SEQUENCE; EFFICIENCY; CONSTRAINTS; THROUGHOUT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Sequence Activities process inputs?

A

PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS,EEF’s, OPA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the components of the Sequence Activities project management plan?

A

SCHEDULE MANAGEMENT PALN, SCOPE BASELINE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the components of the Sequence Activities project documents?

A

ACTIVITY ATTRIBUTES, ACTIVITY LIST, ASSUMPTION LOG,MILESTONE LIST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the Sequence Activities T&T’s?

A

PRECEDENCE DIAGRAMMING METHOD, DEPENDENCY DETERMINATION AND INTEGRATION, LEADS AND LAGS, PROJECT MANAGEMENT INFORMATION SYSTEM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the types of logical relationship in Precedence Diagramming Method (PDM)?

A

FINISH-TO-START, FINISH-TO-FINSH, START-TO-START, START-TO-FINISH

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In PDM, ___ is the most commonly used type of precedence relationship. The ___ relationship is very rarely used.

A

FS; SF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Dependency has __ attributes, but ___ can be applicable at the same time.

A

FOUR; TWO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Mandatory dependencies are those that are ___ or ___ required or inherent in the nature of work

A

LEGALLY; CONTRACTUALLY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

mandatory Dependencies are sometimes referred to as hard logic or hard dependencies. Who does determine which dependencies are mandatory during process of scheduling activities?

A

THE PROJECT TEAM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Discretionary dependencies are established based on knowledge of ___ ___ within a particular application area or some unusual aspect of the project where a specific sequence is ___, even though there may be other ___ sequences.

A

BEST PRACTICES; DESIRED; ACCEPTABLE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When fast tracking techniques are employed, the discretionary dependencies should be reviewed and considered for ____ ____.

A

MODIFICATION OR REMOVAL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

External Dependencies involve a relationship between project activities and ____ activities, which are ___ of team’s control.

A

NON-PROJECT: OUTSIDE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Internal Dependencies involve a ____ relationship between project activities and are generally ___ the project team’s control.

A

PRECEDENCE; INSIDE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A Lead is the amount of time a successor activity can be ____ with respect to a ____ activity.

A

ADVANCED; PREDECESSOR

17
Q

A Lag is the amount of time a ____ activity will be ____ with respect to a predecessor activity.

A

SUCCESSOR; DELAYED

18
Q

What are the Sequence Activities process outputs?

A

PROJECT SCHEDULE NETWORK DIAGRAMS; PROJECT DOCUMENTS UPDATES

19
Q

A project Schedule Network Diagram is a graphical representation of the ____ ___, also referred to as dependencies, among the project schedule activities.

A

LOGICAL RELATIONSHIPS

20
Q

The process of estimating the number of work periods needed to complete individual activities with estimated resources.

A

ESTIMATE ACTIVITY DURATIONS PROCESS

21
Q

The key benefit of this process is that it provides the amount of ____ each activity will take to complete. This process is performed ____ the project.

A

TIME; THROUGHOUT

22
Q

The duration estimate is ___ elaborated, and the process considers the ___ and ___ of the input data.

A

PROGRESSIVELY; QUALITY; INPUT