The process of identifying and documenting relationships among the project activities.
SEQUENCE ACTIVITIES PROCESS
The key benefit of Sequence Activities process is that it defines logical ____ of work to obtain the greatest ____ given all project ____. This process is performed ___ the project.
SEQUENCE; EFFICIENCY; CONSTRAINTS; THROUGHOUT
What are the Sequence Activities process inputs?
PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS,EEF’s, OPA’s
What are the components of the Sequence Activities project management plan?
SCHEDULE MANAGEMENT PALN, SCOPE BASELINE
What are the components of the Sequence Activities project documents?
ACTIVITY ATTRIBUTES, ACTIVITY LIST, ASSUMPTION LOG,MILESTONE LIST
What are the Sequence Activities T&T’s?
PRECEDENCE DIAGRAMMING METHOD, DEPENDENCY DETERMINATION AND INTEGRATION, LEADS AND LAGS, PROJECT MANAGEMENT INFORMATION SYSTEM
What are the types of logical relationship in Precedence Diagramming Method (PDM)?
FINISH-TO-START, FINISH-TO-FINSH, START-TO-START, START-TO-FINISH
In PDM, ___ is the most commonly used type of precedence relationship. The ___ relationship is very rarely used.
FS; SF
Dependency has __ attributes, but ___ can be applicable at the same time.
FOUR; TWO
Mandatory dependencies are those that are ___ or ___ required or inherent in the nature of work
LEGALLY; CONTRACTUALLY
mandatory Dependencies are sometimes referred to as hard logic or hard dependencies. Who does determine which dependencies are mandatory during process of scheduling activities?
THE PROJECT TEAM
Discretionary dependencies are established based on knowledge of ___ ___ within a particular application area or some unusual aspect of the project where a specific sequence is ___, even though there may be other ___ sequences.
BEST PRACTICES; DESIRED; ACCEPTABLE
When fast tracking techniques are employed, the discretionary dependencies should be reviewed and considered for ____ ____.
MODIFICATION OR REMOVAL
External Dependencies involve a relationship between project activities and ____ activities, which are ___ of team’s control.
NON-PROJECT: OUTSIDE
Internal Dependencies involve a ____ relationship between project activities and are generally ___ the project team’s control.
PRECEDENCE; INSIDE