SCHEDULE 4 Flashcards
Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule module for project execution and monitoring and controlling.
DEVELOP SCHEDULE PROCESS
The key benefit of this process is that it generates a ____ ____ with planned ____ for completing project activities, this process is performed ___ project.
SCHEDULE MODULE; DATES; THROUGHOUT
What are the Develop Schedule process inputs?
PROJECT MANAGEMENT PLAN (Schedule management Plan, Scope Baseline), PROJECT DOCUMENTS, AGREEMENTS, EEF’s, OPA’s
What are the components of Develop Schedule project documents?
BASIS OF ESTIMATES; DURATION ESTIMATES; L.L. REGISTER; MILESTONE LIST; PROJECT SCHEDULE NETWORK DIAGRAM; PROJECT TEAM ASSIGNEMENTS; RESOURCE CALENDARS; RESOURCE REQUIREMENTS; RISK REGISTER
What are the Develop Schedule process T&T’s?
SCHEDULE NETWORK ANALYSIS; CRITICAL PATH METHOD; RESOURCE OPTIMIZATION; DATA ANALYSIS; LEADS AND LAGS; SCHEDULE COMPRESSION; PMIS; AGILE RELEASE PLANNING
The overarching technique used to generate the project schedule model.
SCHEDULE NETWORK ANALYSIS
What other methods does Schedule Network Analysis employ?
CRITICAL PATH; RESOURCE OPTIMIZATION TECHNIQUE; MODELING TECHNIQUE
A method used to estimate the minimum project duration and determine the amount of schedule ____ on the logical network paths within schedule module.
CRITICAL PATH METHOD; FLEXIBILITY
The critical paths is the sequence of activities that represents the ___ path through a project, which determines the ____ possible project duration.
LONGEST; SHORTEST
The critical path method is used to calculate the critical path(s) and the amount of ___ and ___ ___ or schedule flexibility on the logical paths within the schedule module.
TOTAL AND FREE FLOAT
The amount of time a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
FREE FLOAT or SLACK
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the ____ ____ ____ or violating a schedule constraint.
TOTAL FLOAT; PROJECT FINSH DATE
A critical path is normally characterized by ____ ___ ___ on the critical path.
ZERO TOTAL FLOAT
Positive Total Float is caused when the backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during forward pass calculation.
POSITIVE TOTAL FLOAT
Negative float analysis is a technique that helps to find possible accelerated ways of bringing a delayed schedule back on track.
NEGATIVE TOTAL FLOAT