SCHEDULE 4 Flashcards

1
Q

Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule module for project execution and monitoring and controlling.

A

DEVELOP SCHEDULE PROCESS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The key benefit of this process is that it generates a ____ ____ with planned ____ for completing project activities, this process is performed ___ project.

A

SCHEDULE MODULE; DATES; THROUGHOUT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Develop Schedule process inputs?

A

PROJECT MANAGEMENT PLAN (Schedule management Plan, Scope Baseline), PROJECT DOCUMENTS, AGREEMENTS, EEF’s, OPA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the components of Develop Schedule project documents?

A

BASIS OF ESTIMATES; DURATION ESTIMATES; L.L. REGISTER; MILESTONE LIST; PROJECT SCHEDULE NETWORK DIAGRAM; PROJECT TEAM ASSIGNEMENTS; RESOURCE CALENDARS; RESOURCE REQUIREMENTS; RISK REGISTER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the Develop Schedule process T&T’s?

A

SCHEDULE NETWORK ANALYSIS; CRITICAL PATH METHOD; RESOURCE OPTIMIZATION; DATA ANALYSIS; LEADS AND LAGS; SCHEDULE COMPRESSION; PMIS; AGILE RELEASE PLANNING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The overarching technique used to generate the project schedule model.

A

SCHEDULE NETWORK ANALYSIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What other methods does Schedule Network Analysis employ?

A

CRITICAL PATH; RESOURCE OPTIMIZATION TECHNIQUE; MODELING TECHNIQUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A method used to estimate the minimum project duration and determine the amount of schedule ____ on the logical network paths within schedule module.

A

CRITICAL PATH METHOD; FLEXIBILITY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The critical paths is the sequence of activities that represents the ___ path through a project, which determines the ____ possible project duration.

A

LONGEST; SHORTEST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The critical path method is used to calculate the critical path(s) and the amount of ___ and ___ ___ or schedule flexibility on the logical paths within the schedule module.

A

TOTAL AND FREE FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The amount of time a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.

A

FREE FLOAT or SLACK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the ____ ____ ____ or violating a schedule constraint.

A

TOTAL FLOAT; PROJECT FINSH DATE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A critical path is normally characterized by ____ ___ ___ on the critical path.

A

ZERO TOTAL FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Positive Total Float is caused when the backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during forward pass calculation.

A

POSITIVE TOTAL FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Negative float analysis is a technique that helps to find possible accelerated ways of bringing a delayed schedule back on track.

A

NEGATIVE TOTAL FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Assign a start date to the start milestone, moving through the network from activity to activity (left to right), assign start and finish dates for each activity. The start and finish dates for each activity is called ___ __ and ___ ___ dates.

A

FORWARD PASS; EARLY START; EARLY FINISH

17
Q

Assign a finish date to the end milestone, then moving back through the network (right to left) it arrives back at the start milestone.

A

BACKWARD PASS

18
Q

The ___ ___ and ___ ___ dates represent the latest dates that each task can start and finish without causing a delay in the finish date of the ____.

A

LATE START; LATE FINISH; PROJECT

19
Q

These techniques are used to adjust the start and finished dates of activities to adjust ____ resource use to be equal or less than resource ____. (Leveling and Smoothing)

A

RESOURCE OPTIMIZATION; PLANNED; AVAILABILITY

20
Q

A resource-optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path.

A

RESOURCE LEVELING

21
Q

A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits.

A

RESOURCE SMOOTHING

22
Q

In resource smoothing, as opposed to resource leveling, the project’s critical path is ___ ___ and the completion date may not be ____.

A

NOT CHANGED; DELAYED

23
Q

Two most often used data analysis techniques?

A

WHAT-IF SCANARIO ANALYSIS; SIMULATION

24
Q

The outcome of the what-if scenario analysis can be used to assess the ___ of the project schedule under different conditions, and in preparing schedule ___ and ___ ___ to address the impact of unexpected situations.

A

FEASIBILITY; RESERVES; RESPONSE PLANS

25
Q

Simulation data analysis technique - models the combined effect of individual ___ ___ and other sources of ____ to evaluate their potential impact on achieving project objectives.

A

PROJECT RSCKS; UNCERTAINITY

26
Q

Simulation technique in which risks and other sources of uncertainty are used to calculate possible schedule outcomes for the total project.

A

MONTE CARLO ANALYSIS

27
Q

Leads are used in limited circumstances to ____ a successor activity with respect to the predecessor activity.

A

ADVANCE

28
Q

Lags are used in limited circumstances where processes require a set period of time to ____ ___ the predecessor and successors without work or resource impact.

A

ELAPSE BETWEEN

29
Q

Schedule compression techniques are used to ____ or ____ the schedule duration without reducing the project scope in order to meet schedule constraints, imposed dates, or other schedule objectives.

A

SHORTEN; ACCELERATE

30
Q

A schedule compression technique used to shorted the schedule duration for the least incremental cost by adding additional resources. Examples: overtime, bringing additional resources, etc.

A

CRASHING

31
Q

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

A

FAST TRACKING

32
Q

What are the Develop Schedule process outputs?

A

SCHEDULE BASELINE; PROJECT SCHEDULE; SCHEDULE DATA; PROJECT CALENDARS; CHANGE REQUESTS; PMP UPDATES; PROJECT DOCUMENTS UPDATES

33
Q

The process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline.

A

CONTROL SCHEDULE PROCESS

34
Q

The key benefit of Control Schedule process is that the ____ ____ is maintained throughout the project, this process is performed ___ the project.

A

SCHEDULE BASELINE; THROUGHOUT

35
Q

What are the Control Schedule process inputs?

A

PROJECT MANAGEMENT PLAN; PROJECT DOCUMENTS; WORK PERFORMANCE DATA; OPA’s

36
Q

What are the Control Schedule T&T’s?

A

DATA ANALYSIS; CRITICAL PATH METHOD; PMIS; RESOURCE OPTIMIZATION; LEADS AND LAGS; SCHEDULE COMPRESSION

37
Q

What are the components for Control Schedule data analysis T&T’s?

A

EARNED VALUE ANALYSIS (SV, SPI); ITERATION BURNDOWN CHART; PERFORMANCE REVIEWS; TREND ANALYSIS; VARIANCE ANALYSIS; WHAT-IF SCENERIO ANALYSIS

38
Q

What are the Control Schedule process outputs?

A

SCHEDULE FORECASTS; CHANGE REQUESTS; PMP UPDATES; PROJECT DOCUMENTS UPDATES