INTEGRATION 2 Flashcards

1
Q

Determining corrective or preventive actions or re-planning and following upon action plans to determine if the actions taken resolved the performance issue.

A

CONTROL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Collecting, measuring, and assessing measurements and trends to effect process improvements.

A

MONITOR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Monitor and Control Project Work process inputs?

A

PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS, WORK PERFORMANCE INFORMATION, AGREEMENTS, EEF’s, OPA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Monitor and Control Project Work process outputs?

A

WORK PERFORMANCE REPORTS, CHANGE REQUESTS, PROJECT MANAGEMENT PLAN UPDATES, PROJECT DOCUMENTS UPDATES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Process of reviewing all change requests; approving changes and managing changes to deliverables, project documents, and the project management plan; and communicating the decisions.

A

PERFORM INTEGRATED CHANGE CONTROLL PROCESS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the Perform Integrated Change Control process inputs?

A

PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS, WORK PERFOMANCE REPORTS, CHANGE REQUESTS, EEF’s, OPA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The change management plan provides the direction for managing the change control process and documents the roles and responsibilities of the _____ .

A

CHANGE CONTROLL BOARD (CCB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the Perform Integrated Change Control process outputs?

A

APPROVED CHANGE REQUESTS, PROJECT MANAGEMENT PLAN UPDATES, PROJECT DOCUMENTS UPDATES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Process of finalizing all activities for the project, phase, or contract.

A

CLOSE PROJECT OR PHASE PROCESS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the Close Project or Phase process inputs?

A

PROJECT CHARTER, PROJECT MANAGEMENT PLAN, PROJECT DOCUMENTS, ACCEPTED DELIVERABLES, BUSINESS DOCUMENTS, AGREEMENTS, PROCUREMENT DOCUMENTATION, OPA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the Close Project or Phase process outputs?

A

PROJECT DOCUMENTS UPDATES, FINAL PRODUCT, SERVICE, OR RESULT TRANSITION, FINAL REPORT, OPA’s UPDATES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

On a large or complex projects, a ______ is set up and is responsible for reviewing and approving or rejecting change requests.

A

CHANGE CONTROLL BOARD (CBB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly