Schedule 2 Flashcards
What is the finished and approved schedule called?
The Schedule Baseline
A Gantt Chart allows you to compare what to the schedule?
progress
What is a burn up chart?
It shows the amount of work completed versus the total amount of work planned for a project.
Visual of how much work has been completed and how much remains to be done.
What is a burn down chart?
Focuses on the remaining work and is ideal for understanding how much work is left to complete.
What is a type of bar chart which illustrates a project timeline or schedule with resources?
a Gantt Chart?
You are managing a project and need to communicate key achievements and deadlines to stakeholders. Which of the following tools is best suited for showing significant project milestones and their deadlines without providing detailed information on all project activities?
A. Gantt Chart
B. Milestone Chart
C. Network Diagram
D. Burn-Down Chart
B. Milestone Chart
You are managing a project and need to accelerate the schedule to meet a critical deadline. You are considering two schedule compression techniques: crashing and fast tracking. Which of the following statements accurately describes the impact of these techniques on project cost and risk?
A. Crashing increases both cost and risk; fast tracking increases cost but reduces risk.
B. Crashing increases cost but does not affect risk; fast tracking increases both cost and risk.
C. Crashing increases cost; fast tracking increases risk but does not affect cost.
D. Crashing increases cost; fast tracking increases both cost and risk.
C. Crashing increases cost; fast tracking increases risk but does not affect cost.
You are managing a project and encounter a situation where a key team member who performs a critical function becomes unexpectedly unavailable for a week. You need to adjust the project schedule to accommodate this issue. Which of the following techniques would be appropriate for addressing this situation, and why?
A. Use crashing to add additional resources and minimize the impact on the project schedule.
B. Use fast tracking to perform tasks in parallel and mitigate the delay.
C. Use smoothing to adjust activities within float to accommodate the delay without affecting the overall project finish date.
D. Use schedule compression to shorten the project duration and absorb the impact of the delay.
C. Use smoothing to adjust activities within float to accommodate the delay without affecting the overall project finish date.
During a project, you encounter a situation where unexpected events, such as equipment failure or team member illness, force you to adjust the project schedule. You need to determine how to handle this adjustment. Which of the following techniques is appropriate for managing such situations, and what is the primary impact of using this technique?
A. Use smoothing to adjust activities within available float without impacting the project’s finish date.
B. Use crashing to add resources and accelerate the project schedule.
C. Use fast tracking to perform tasks in parallel to mitigate delays.
D. Use resource leveling to adjust the schedule, which may result in extending the project duration to accommodate the unexpected events.
D. Use resource leveling to adjust the schedule, which may result in extending the project duration to accommodate the unexpected events.
Leveling lengthens the schedule, and is usually used equipment is an issue, or the one person with a special skill gets sick, etc.
In an Agile project, the project owner and the team are involved in determining the number of sprints or releases. Which of the following statements best describes the role of the project owner and team in this decision-making process?
A. The project owner alone decides the number of sprints or releases based on the project’s requirements and deadlines.
B. The team decides the number of sprints or releases based on their capacity and velocity, while the project owner approves the plan.
C. The project owner and team collaboratively decide on the number of sprints or releases based on project scope, priorities, and capacity.
D. The project manager determines the number of sprints or releases, with input from the project owner and team on the project’s scope.
C. The project owner and team collaboratively decide on the number of sprints or releases based on project scope, priorities, and capacity.
You are managing a project and need to communicate the overall project strategy and major deliverables to stakeholders. Which of the following tools is most appropriate for showing planned releases and their associated timeframes throughout the project lifecycle?
A. Gantt Chart
B. Roadmap
C. Work Breakdown Structure (WBS)
D. Network Diagram
B. Roadmap
Roadmap shows releases and timeframes
You are reviewing a project schedule and come across a chart that displays a list of project tasks along with their start and end dates, dependencies, and progress. The chart also includes horizontal bars that represent the duration of each task, with bars spanning across a timeline to show when each task is scheduled to occur. Which of the following tools are you most likely looking at?
A. Gantt Chart
B. Milestone Chart
C. Burn-Down Chart
D. Resource Histogram
A. Gantt Chart
Provides a visual representation of the project schedule, showing task durations and dependencies, but it is less focused on depicting the sequence of activities compared to a network diagram.
You are in the process of planning a project and need to break down the project deliverables into smaller, manageable components. Which of the following tools or techniques is most appropriate for achieving this and ensuring that all project work is captured and organized?
A. Gantt Chart
B. Work Breakdown Structure (WBS)
C. Network Diagram
D. Resource Breakdown Structure (RBS)
B. Work Breakdown Structure (WBS)
Breaks down the project deliverables into smaller components but does not illustrate task dependencies or sequences.
You are managing a project and need to visualize the sequence and dependencies of project activities to determine the critical path and overall project duration. Which of the following tools is best suited for this purpose?
A. Gantt Chart
B. Milestone Chart
C. Network Diagram
D. Work Breakdown Structure (WBS)
C. Network Diagram
This tool is used to depict the sequence of project activities and their dependencies. It helps in identifying the critical path, understanding the flow of tasks, and determining the overall project duration.
You need to present the key achievements and deadlines of a project to stakeholders in a high-level overview format, without detailing all the tasks and dependencies. Which of the following tools is best suited for this purpose?
A. Gantt Chart
B. Network Diagram
C. Work Breakdown Structure (WBS)
D. Milestone Chart
D. Milestone Chart
This tool provides a high-level overview of key project milestones and their associated deadlines. It highlights significant achievements and deadlines without delving into detailed tasks and dependencies, making it ideal for presenting a summary to stakeholders.