Schedule 1 Flashcards

1
Q

To build a Schedule, what gets organized?

A

Activities and tasks of the Work Package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are the tasks arranged in a Network Scheduled Diagram?

A

in a logical path
(see diagram study tab)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the document stating how to define tasks & activities?

A

the Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is it called to use similar past examples of the Schedule Management Plan from other projects to give the schedule a starting point?

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is used to learn lessons from completed projects in the organization?

A

Historical Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Once the logical order for the Schedule mgmt plan is established, we determine dependencies. What are the two types of dependencies?

A

Mandatory
Discretionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define a Mandatory dependency

A

MUST do step one before step 2

  • Contract specifies client approval before you move onto next task
  • Compliance inspection after a task complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define a Discretionary dependency

A

prefer for step 1 to come before step 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

True or false, dependencies can be both Internal and External?

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which task dependency is the most common?
- finish to finish
- start to finish
- finish to start
- start to start

A

Finish to Start: A task cannot start until a previous task is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is it called when a task cannot start until a previous task is completed.

A

Finish to start (FS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is it called when a task cannot finish until another task is completed.

A

Finish-to-finish (FF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is it called when a task cannot start until another task begins.

A

Start-to-start (SS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is it called when a task cannot finish until another task starts.

A

Start-to-finish (SF)

This is an uncommon type of dependency, usually found in scheduling-related events where there is a handover between tasks. For example, an initial output from task B may be required for the final part of task A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the time it takes to do a task?

A

Task Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When looking at estimate durations for tasks, there are 4 methods. One of them is Analogous, what is this method known for?

A

Being inaccurate. Only used when limited project info is known. Based on historical calculations.

17
Q

In a Parametric method, what is used to calculate task durations?

A

a computer algorithm

18
Q

What is the most likely type of estimate duration for tasks, and what does it incorporate?

A

three-point

optimistic, pessimistic, most likely
(see formulas tab)

19
Q

In a Bottom-up method, what is used to calculate task durations?

A

the WBS dictionary, review tasks and activities we have, and determine what everything will cost in terms of time.

20
Q

How do you calculate Triangular Distribution (of days it takes to do a task)?

A

(O+ML+P)/3 = # of days to do the task

Optimistic = O
Most Likely = ML
Pessimistic = P

21
Q

How do you calculate Pert (Beta) Distribution (of days it takes to do a task)?

A

Weighted Average is called BETA or PERT Distribution
(O+4M+P)/6

(O+M+M+M+M+P)/6
Optimistic = O
Most Likely = ML
Pessimistic = P

22
Q

Quiz: Estimate Durations
(time it takes to do tasks)
Optimistic = 8
Most Likely = 14
Pessimistic = 26

Calculate Triangular + BETA

A

Triangular: 16
BETA: 15

23
Q

What is a gap in time between to tasks?

A

Lag

24
Q

What is an overlap of two tasks; occurring simultaneously?

A

Lead

25
Q

What is the definition of Critical Path Method (CPM)?

A

The longest one.
Used to identify the longest it could possibly take to complete a project.
(see chart tab)

26
Q

What is is the maximum amount of time an activity can be delayed without delaying the project?

A

Total Float

27
Q

What is the amount of time an activity can be delayed without
impacting the Early Start date of any of its immediate successors?

A

Free Float

28
Q

Can a task can have both Free Float and Total Float?

A

Yes, they are independent of one another

29
Q

How much total float does an activity have on the critical path?

A

0

30
Q

In CPM (critical path method), what is it called to tie up loose ends at before a release?

A

Iteration H or Hardening Sprint

31
Q

In CPM (critical path method), what is it called when no changes can happen and work on tasks needs to stop for a time?

A

Black-out times
Usually when users are testing