Hybrid Approach Flashcards

1
Q

Define the Hybrid Approach

A
  • Combination of Traditional and Iterative (requires stakeholder coaching)
  • Some phases are known, some are not
  • An agile project that happens within a traditional project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A hybrid project overall framework is most like which type of project? Who leads?

A

Traditional, led by Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In a hybrid project, who makes sure all the work gets done/action happens during the sprint?

A

the scrum master

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which approach, Traditional or Iterative?
Sponsor

A

Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which approach, Traditional or Iterative?
Project Manager

A

Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which approach, Traditional or Iterative?
Product (project) owner

A

Iterative/agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which approach, Traditional or Iterative?
Scrum master

A

Iterative/agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which approach, Traditional or Iterative?
Predictive

A

Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which approach, Traditional or Iterative?
Rolling wave

A

Iterative/agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which approach, Traditional or Iterative?
Deliverable at the end

A

Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which approach, Traditional or Iterative?
Launch at the end

A

Iterative/Agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When should a project manager consider using Agile methodologies over Waterfall?
A. When the project scope is well-defined and stable.
B. When frequent customer collaboration and flexibility are critical.
C. When the project has a strict timeline and budget constraints.
D. When the project team prefers detailed documentation and upfront planning.

A

B. When frequent customer collaboration and flexibility are critical.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In which scenario would a predictive (Waterfall) project management approach be more appropriate?
A. Developing a new software application with evolving requirements.
B. Constructing a bridge with detailed engineering specifications.
C. Organizing a marketing campaign requiring rapid iterations.
D. Implementing a research project with unclear deliverables.

A

B. Constructing a bridge with detailed engineering specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly