EV Focus Flashcards

1
Q

EV

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC

A

Estimate at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ETC

A

Estimate to Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Earned Value?

A

value of work completed; the measure of work performed expressed in terms of the budget
authorized for that work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Planned Value

A

value of work planned (i.e. baseline); the authorized budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Actual Cost?

A

the money spent/paid/missing from your budget; the realized cost incurred for the work performed on an activity during a specific time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Budget at Completion?

A

planned budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Estimate at Completion?

A

revised final budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Estimate to Completion?

A

money needed to get to completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is SV?

A

schedule variance; measures performance – by calculating the difference between EV and PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is SPI?

A

Schedule performance index measures efficiency by calculating the ratio of EV to PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is the project on budget?
Use CV to calculate

A

Cost Variance
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How efficient is my project? ‘
Use CPI to calculate

A

Cost Performance Index
CPI = EV / AC

17
Q

What is CPI?

A

Cost Performance Index

18
Q

If CV value = 0, is the project on budget or under budget?

A

on budget

19
Q

If CPI value = 1, is the project on budget or over budget?

A

on budget

20
Q

What will the project cost in total?
use EAC

A

Estimate at Completion
EAC = BAC/CPI
or
EAC = ETC + AC

21
Q

How much more cost is required to complete the remainder of the project? Use ETC

A

Estimate to Complete
ETC = EAC - AC

{pg 241 example about Anna: ETC = (BAC-EV)/CPI}

22
Q

What does a negative value mean when looking at Schedule Variance SV?

A

It means behind schedule, the scope took longer to do than you thought it would.

23
Q

Calculate SV

A

SV = EV - PV