Resource loading and leveling Flashcards

1
Q

When resource loading and leveling, what is the priority rule that maximizes the number of tasks completed in a given time?

A

Shortest duration first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When resource loading, you should make sure the calendar reflects reality regarding the following:
1. Hours / day
2. ___________
3. Holidays / Vacation

A

work week

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When resource loading, issues that can cause hours required to exceed capacity include the following:
1. Illness
2. Change Orders
3. Worker not ready
4. _______ not ready

A

task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When resource loading, issues that can cause hours required to exceed capacity include the following:
1. Illness
2. ___________ Orders
3. Worker not ready
4. task not ready

A

change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When resource loading, issues that can cause hours required to exceed capacity include the following:
1. ____________
2. Change Orders
3. Worker not ready
4. task not ready

A

Illness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When resource loading, you should look for opportunities including the following:
1. Longer hours
2. _________
3. Weekends

A

additional resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When resource loading, you should look for problems including the following:
1. Overloading of a resource
2. ___________
3. Unavailable days

A

Unavailable hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When resource leveling, you should make MS Project a [x], not a burden

A

Tool

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Do scarcity of resources typically apply to resources in general?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When resource loading and leveling, what is the priority rule that uses LST for activity start?

A

As late as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When resource loading and leveling, what is the priority rule that minimizes the number of late activities?

A

Minimum slack first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When resource loading, you should make sure the calendar reflects reality regarding the following:
1. Hours / day
2. Work week
3. _______ / _________

A

Holidays, Vacation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When resource loading, you should look for opportunities including the following:
1. __________
2. Additional resources
3. Weekends

A

Longer hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Is task duration necessarily dictated by the amount of labor required to complete the task?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When resource loading and leveling, what is the priority rule that assumes that important activities have greater demand of resources?

A

Most resources first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When resource loading, you should make sure the calendar reflects reality regarding the following:
1. [x] / [y]
2. Work week
3. Holidays / Vacation

A

Hours / Day

17
Q

When resource loading and leveling, what is the priority rule that focuses on activities that could cause greatest damage to the timeline?

A

Most Critical Followers

18
Q

When resource loading, MS Project defaults to a work day of _______ am to _______pm with lunch from ________ to ________pm.

A

8, 5, 12, 1

19
Q

When resource loading and leveling, what is the priority rule that uses EST for activity start?

A

as soon as possible

20
Q

When resource loading, issues that can cause hours required to exceed capacity include the following:
1. Illness
2. Change Orders
3. _________ not ready
4. Task not ready

A

worker

21
Q

When resource loading, you should look for problems including the following:
1. _________
2. Unavailable hours
3. Unavailable days

A

Overloading of a resource

22
Q

When resource loading, MS Project assumes the resource is dedicated [x]% to the project.

A

100

23
Q

When resource loading, you should look for opportunities including the following:
1. Longer hours
2. Additional resources
3._________

A

Weekends

24
Q

When resource loading, you should look for problems including the following:
1. Overloading of a resource
2. Unavailable hours
3. __________

A

unavailable days

25
Q

When resource loading, you should expect problems, if you schedule to the theoretical [x]

A

Maximum

26
Q

Is task duration necessarily dictated by the calendar time required to complete the task?

A

Yes