Precedence Diagramming Flashcards

1
Q

In precedence diagramming, the [x] linkage is the most common.

A

Finish-to-start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In precedence diagramming, the [x] linkage is when the activity starts based on the predecessor activity’s finish time.

A

Finish-to-start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In precedence diagramming, the [x] linkage is when the activity finishes based on the successor activity’s start time.

A

Start-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In precedence diagramming, the [x] linkage is when the two activities start at the same time.

A

Start-to-start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In precedence diagramming, the [x] linkage is when the two activities end at the same time.

A

Finish-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly