Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. Reduce the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of bottleneck resources
3. Reduce the amount of _______ added to individual tasks and then add some fraction back as _________

A

Safety time, project buffer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key _________ not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for resources

A

Resources and Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key resources and data not available
4. unrealistic __________, thus often exceeded
5. always competing with other projects for resources

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. Reduce the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of __________ resources
3. Reduce the amount of safety time added to individual tasks and then add some fraction back as project buffer

A

Bottleneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for __________

A

resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project ____________
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for resources

A

Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project ___________
2. too many changes to project scope
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for recources

A

due dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. ___________ the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of bottleneck resources
3. Reduce the amount of safety time added to individual tasks and then add some fraction back as project buffer

A

reduce

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The _________ Curve project lifecycle has a slow start and a quick finish

A

J

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The ______ Curve project lifecycle has a slow start, quick momentum, and a slow finish.

A

S

How well did you know this?
1
Not at all
2
3
4
5
Perfectly