Goldratt and Critical Chain Flashcards
Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. Reduce the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of bottleneck resources
3. Reduce the amount of _______ added to individual tasks and then add some fraction back as _________
Safety time, project buffer
Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key _________ not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for resources
Resources and Data
Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key resources and data not available
4. unrealistic __________, thus often exceeded
5. always competing with other projects for resources
Budget
Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. Reduce the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of __________ resources
3. Reduce the amount of safety time added to individual tasks and then add some fraction back as project buffer
Bottleneck
Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project scope
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for __________
resources
Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project due dates
2. too many changes to project ____________
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for resources
Scope
Goldratt identified some similar issues that troubled people about working on projects regardless of the type of project which included the following:
1. unrealistic project ___________
2. too many changes to project scope
3. key resources and data not available
4. unrealistic budget, thus often exceeded
5. always competing with other projects for recources
due dates
Some of the techniques recommended by Goldratt to reverse the cycle of project problems include the following:
1. ___________ the number of projects assigned to each individual
2. Schedule the start of new projects based on the availability of bottleneck resources
3. Reduce the amount of safety time added to individual tasks and then add some fraction back as project buffer
reduce
The _________ Curve project lifecycle has a slow start and a quick finish
J
The ______ Curve project lifecycle has a slow start, quick momentum, and a slow finish.
S