AOA and AON Flashcards

1
Q

In order to calculate the LST/LS and LFT/LF in an AON, you use the [x] pass.

A

Backward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In an AON, EFT stands for [x]

A

Earliest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In an AON, EST stands for [x]

A

Earliest Start Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When sorting out a project by identifying all of the tasks, you should engage in a [x] planning process.

A

Hierarchical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When sorting out a project by identifying all of the tasks, you should begin with the project’s [x].

A

Objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

[x] is a series of connected activities (or intermediate events) between any two events in a network.

A

Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In an AON, LFT stands for [x]

A

Latest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

AON stands for [x]

A

Activity on Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In order to calculate the EST/ES and EFT/EF in an AON, you use the [x] pass.

A

Forward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

[x] is a task or set of tasks required by the project which use resources and time.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Do you want there to be Negative Float?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Free slack is the slack an activity has before it delays the [x]

A

Next Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

[x] is the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When sorting out a project by identifying all of the tasks, the lowest level task is typically [x] to [y] days in duration.

A

2, 14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Do you want there to be more than one critical path?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

[x] is a diagram of nodes connected by directional arcs that defines the project and illustrates the relationships of all activities.

A

Network

17
Q

In an AON, LST stands for [x]

A

Latest Start time

18
Q

What is the Duration of a Milestone?

A

0

19
Q

When sorting out a project by identifying all of the tasks, you generally use [x] to [y] activities per level

A

5 to 15

20
Q

[x] are identifiable and noteworthy events marking significant progress on the project.

A

Milestones

21
Q

AOA stands for?

A

Activity on Arrow

22
Q

Can there be negative float

A

Yes

23
Q

Can a critical path run over a dummy task?

A

Yes

24
Q

Can a critical path change?

A

Yes

25
Q

[x] is the time required to complete all activities on the critical path.

A

Critical Time

26
Q

How much float does the critical path have?

A

0

27
Q

Total slack is the slack an activity has before it delays the [x].

A

Project

28
Q

[x] is an identifiable state resulting from the completion of one or more activities. Before it can be achieved or realized, all its predecessor activities must be completed.

A

Event

29
Q

Can there be more than one critical path?

A

Yes