Project Management Processes Flashcards
Name the two Initiating processes.
- Develop Project Charter - Identify Stakeholders
Name the only Closing group processes.
Close Project or Phase
What is the total number of project management processes defined in the PMBOK® Guide, 6th Edition?
49 processes, across 5 Process Groups and 10 Knowledge Areas
Name the Project Integration Management process(es) under the Initiating Process Group.
Develop Project Charter
Name the Project Integration Management process(es) under the Planning Process Group.
Develop Project Management Plan
Name the Project Integration Management process(es) under the Executing Process Group.
- Direct and Manage Project Work - Manage Project Knowledge
Name the Project Integration Management process(es) under the Monitoring and Controlling Process Group.
- Monitor and Control Project Work - Perform Integrated Change Control
Name the Project Integration Management process(es) under the Closing Process Group.
Close Project or Phase
Name the Project Scope Management processes under the Planning Process Group.
- Plan Scope Management - Collect Requirements - Define Scope - Create WBS
Name the Project Scope Management process(es) under the Monitoring and Controlling Process Group.
- Validate Scope - Control Scope
Name the Project Schedule Management processes under the Planning Process Group.
- Plan Schedule Management - Define Activities - Sequence Activities - Estimate Activity Durations - Develop Schedule
Name the Project Schedule Management process(es) under the Monitoring and Controlling Process Group.
Control Schedule
Name the Project Cost Management process(es) under the Planning Process Group.
- Plan Cost Management - Estimate Costs - Determine Budget
Name the Project Cost Management process(es) under the Monitoring and Controlling Process Group.
Control Costs
What is/are the Project Quality Management process(es) under the Planning Process Group?
Plan Quality Management
What is/are the Project Quality Management process(es) under the Executing Process Group?
Manage Quality
What is/are the Project Quality Management process(es) under the Monitoring and Controlling Process Group?
Control Quality
Name the Project Resource Management process(es) under the Planning Process Group.
- Plan Resource Management - Estimate Activity Resources
What is/are the Project Resource Management process(es) under the Executing Process Group? (3)
1) Acquire Resources
2) Develop Team
3) Manage Team
What is/are the Project Stakeholder Management process(es) under the Initiating Process Group?
Identify Stakeholders
What is/are the Project Communications Management process(es) under the Planning Process Group?
Plan Communications Management
What is/are the Project Communications Management process(es) under the Executing Process Group?
Manage Communications
Name the Project Communications Management process(es) under the Monitoring and Controlling Process Group.
Monitor Communications
Name the Project Risk Management process(es) under the Planning Process Group.
- Plan Risk Management - Identify Risks - Perform Qualitative Risk Analysis - Perform Quantitative Risk Analysis - Plan Risk Responses
Name the Project Risk Management process(es) under the Monitoring and Controlling Process Group.
Monitor Risks
What is/are the Project Procurement Management process(es) under the Planning Process Group?
Plan Procurement Management
What is/are the Project Procurement Management process(es) under the Executing Process Group?
Conduct Procurements
What is/are the Project Procurement Management process(es) under the Monitoring and Controlling Process Group?
Control Procurements
What is/are the Project Procurement Management process(es) under the Closing Process Group?
There is no Project Procurement Management process under the Closing Process Group.
What is the primary source of information for how the project will be planned, executed, monitored and controlled, and closed?
The Project Management Plan
Which is the process that usually follows the Collect Requirements process?
Define Scope
Which Project Schedule Management processes usually precede the Develop Schedule process in the Planning Process Group? (4)
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activity Durations
Name all the Project Quality Management processes.
- Plan Quality Management - Manage Quality - Control Quality