Earned Value Management Flashcards

1
Q

What is the Schedule Variance (SV) at the end of a completed project?

A

Zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does a negative (-) Schedule Variance (SV) indicate?

A

The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does a positive (+) Schedule Variance (SV) indicate?

A

The project is ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three Earned Value Management (EVM) types used for measuring work performance?

A
  • Apportioned Effort
  • Discrete Effort
  • Level of Effort (LOE)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a negative (-) Cost Variance (CV) indicate?

A

The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does a positive (+) Cost Variance (CV) indicate?

A

The project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Cost Variance (CV) at the end of a project?

A

BAC minus Actual amount spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does a Schedule Performance Index (SPI) value of less than 1 indicate?

A

The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a Schedule Performance Index (SPI) value of more than 1 indicate?

A

The project is ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does a Cost Performance Index (CPI) value of less than 1 indicate?

A

The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does a Cost Performance Index (CPI) value of more than 1 indicate?

A

The project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is typically the shape of EV data curve of a project when plotted against time?

A

S-curve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the cost forecast indicator in Earned Value Management?

A

Estimate At Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does Variance at Completion (VAC) tell about a project?

A

It tells how much over or under budget the project is expected to be at the end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does Estimate to Complete (ETC) tell about a project?

A

It tells how much the remaining work on the project is expected to cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does Cost Performance Index (CPI) indicate?

A

Cost efficiency of the project

17
Q

What is the most critical EVA metric?

A

Cost Performance Index (CPI)