Low Difficulty Flashcards
QA
Quality Assurance
QC
Quality Control
ID
Activity Identifier
IT
Information Technology
PM
Project Manager / Project Management
PMBOK®
Project Management Body Of Knowledge
PMI®
Project Management Institute
What are Acceptance Criteria?
A set of conditions that is required to be met before deliverables are accepted.
What is an Activity?
A distinct, scheduled portion of work performed during the course of a project.
What is Activity Duration?
The time in calendar units between the start and finish of a schedule activity. In simple terms, it’s the length of time that it takes to complete an activity.
What is an Activity Identifier?
A unique identifier for each schedule activity in a schedule network diagram.
What is an Assumption?
A factor that is considered to be true or certain for the purpose of planning, without demonstration or proof.
Who is a Buyer?
The owner of the final product, a subcontractor, the acquiring organization, a service requestor, or the purchaser.
What is a Calendar Unit?
The unit of time used in scheduling a project. Example hours, days, weeks, months, etc.
What are Criteria?
Standards, rules, or tests used as a basis for decision making, or for evaluating a product, service, result, or process.
What is the definition of a Defect?
An anomaly or flaw, in a deliverable such that the deliverable does not meet its requirements or specifications.
Define Duration (DU or DUR).
The total number of work periods (days, weeks, etc.), excluding holidays or other nonworking periods, required to complete an activity or work breakdown structure component.
Define Effort.
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.
What is a Finish Date?
The date of completion of a schedule activity, usually qualified by one of the eight following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
Define Forecast.
An estimate or prediction of future conditions and events in a project based on project’s performance, and other information available at the time of the forecast.
Define Issue.
A current condition or situation that may have an impact on the project objectives.
What is a Log?
A document used to record and track selected items (like changes, issues, etc.) during the execution of a process or an activity. Usually used with a modifier, such as issue, change, issue, or assumption.
What is a Milestone?
A significant point or event in a project, program, or portfolio, for example, completing a key deliverable.
What is Percent Complete?
The ratio of the estimated amount of work completed to the total estimated work on an activity or a WBS component, expressed in percentage.
What is a Preventive Action?
An intentional activity that ensures the future performance of the project work is aligned with the Project Management Plan.
What is a Resource?
Everything needed to complete a project. Examples include human resources, equipment, services, supplies, material and funds.
Define Result.
An output of a project management process or an activity. It could be an outcome (e.g. a business process, an upgraded system, a research study, a trained resource, etc.) or a document (e.g. a new policy document, a training plan, a research report, etc.).
Define Rework.
Action taken to bring a defective or non-conforming component into compliance with requirements or specifications.
What is a Schedule?
A generic term for project schedule, or schedule model.
What is a Start Date?
The start date of a schedule activity, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
What is a Successor Activity?
A dependent activity that logically comes after another activity in a schedule. In other words, it’s the “to” activity of a logical relationship in a schedule network.