project management process interactions Flashcards

1
Q

What is the span of Executing process group?

A

This process group spans throughout the project life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is monitoring and controlling process groups span?

A

throughout project lifecycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when does closing process start?

A

after initiating process ends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Are process groups within project life-cycle discrete elements without any overlap?

A

No they tend to overlap each other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

are process groups and project phases same?

A

No. process groups represent the type of phases that take place within a project
within each process group, there are the phases that a project must go through
Each phase of a project might require all process groups to be executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is constant in a project?

A

Change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens when change occurs?

A

processes need to be applied on the change as if they were originally part of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what are the implications of a change?

A

1.Additional time

  1. Impact project’s schedule as below
    - Develop Schedule
    - Control Schedule
    - Estimate Costs
    - Budget
    - Procurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project quality management process spans across what all process groups?

A

planning (plan quality management)
executing (perform quality assurance)
monitoring & control (control quality)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can project manager manage change when they don’t even know what changes could come across?

A
Using Process Assets that allow you to:
Formally accept change
Integrate change and minimize the impact
Promote an approval process
Maximize the value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who normally approves the change?

A

Change Control Committee - that consists of SME, and project team members that determine risk reward ratio to decide if the change should be progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What happens if the change is not approved?

A

It could be progressed on a separate project

or no action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you determine if a change needs to be accepted or not?

A

Ask the question if the project can be delivered successfully without the change.
If not, a integrated change control process need to be initiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What typical activities a PM does when change comes in (example of doubling the size of the house being constructed)

A

Negotiate with team and suppliers
May bring materials from other source
project budget will be impacted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What PM has to do when a change is not feasible?

A

provide alternatives. Arrive at sceanrios with the help of the team. E.g.
Good: The sponsor accepts the original plan and moves
in upon its completion
Better: The sponsor continues with the original plan
then sells, using the proceeds to fund a larger project
at a later time
Best: The project is placed on hold for the winter to provide
the project manager more time to meet the sponsor’s
new requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

_________ pertains to a general agreement that the application of project management processes has been known to enhance productivity and the probability of success for a wide range of projects.

A

Good practice