Formulae And Terminology Flashcards
1
Q
Monte Carlo analysis
A
Section 11.4.2.2
2
Q
3 point estimates
A
Section 6.5.2.4
3
Q
SPI (Schedule performance index)
A
Earned Value(EV)/Planned Value (PV)
4
Q
CPI (Cost Performance Index)
A
EV/Actual Cost