7.3 Determine Budget Flashcards

1
Q

What is Determine Budget process?

A

It is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the benefit of Determine Budget process?

A

It determines the cost baseline against which project performance can be monitored and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does cost management plan contain ?

A

It contains a description of how the project costs will be managed and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does Scope Baseline help with determine budget?

A

It contains project scope statement which describes the formal limitations by period for the expenditure of project funds mandated by the organisation, by agreement or by other entities such as government agencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the inputs to Determine Budget process?

A
/cost management plan
/cost baseline 
/activity cost estimates 
/basis of estimates 
/project schedule 
/resource calendars
/risk register
/agreements
/organisational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the tools used for Determining budget?

A
cost aggregation 
Reserve analysis 
Expert judgment 
Historical relationship 
Funding limit reconciliation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Funding Limit Reconciliation tool used for?

A

It is used for determining budget by reconciling the expenditure of funds with any funding limits on the commitment of funds for the project. A variance between planned expenditure and the funding limit will necessitate rescheduling of work to level out the rate of expenditure. This is done by placing imposed date constraints on the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the outputs of determine budget process?

A

/cost baseline
/project funding requirements
/project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is cost baseline made up of

And how budget is arrived from this?

A
/Activity level cost estimates 
/activity level contingency reserves 
/work packages level costs
/work packages level contingency reserves 
/control account costs

Budget is arrived from this by adding Managemet reserves to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does funding requirements include?

A

It includes total funding requirements and periodic funding requirements.
It may also include the source of funding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the project documents updated as part of Determine Budget process?

A

/Risk Register
/Activity Cost Estimates and,
/Project Schedule