6.6 develop schedule Flashcards

1
Q

schedule network analysis

A

technique that generates the project schedule model. employs analytical techniques - CPM, CCM(Critical chain method), what if analysis, and resource optimisation techniques to calculate early and late start and finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical path method

A

Method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network path within the schedule model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Critical path

A

Sequence of activities that represent longest path through a project, which determines shortest possible project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the inputs to schedule development

A
Schedule management plan
Activity list
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Risk register
Project staff assignment
Resaws breakdown structure
Enterprise environmental factors
Organisational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop schedule - tools and techniques

A
Schedule network analysis
Critical path method
Critical chain method
Resource optimisation techniques
Resource smoothing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical path method

A

Critical path method is the method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network parts within the schedule model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What calculations are done in the critical path method?

A

It calculates really start early finish late start late finish dates for all activities by doing a forward and back word pass analysis through the network schedule without regard for any resource constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the main purpose of critical path method

A

The critical path method is used to calculate the amount of scheduling flexibility on the logical network paths within the schedule model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is ‘total float’

A

On any network schedule the schedule flexibility is measured by the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint, and is termed ‘total float’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

As implemented using PDM (precedence diagramming method) method, what are the possible float values in a critical path

A

Critical path could have positive, negative or zero float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When do you get a positive total float in critical path method?

A

Positive total float is caused when the backward pass is calculated from the schedule constraint that is later than the early finish date that has been calculated using the forward pass calculation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When do we get negative total float

A

Negative total float is caused when a constraint on the late dates is violated by duration and logic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do we produce network paths with zero or positive total float?

A

Adjusting activity durations with more resources or less scope

Checking if logical relationship can be discretionary

Leads and lags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is free float

A

Amount of time that a scheduled activity can be delayed without delaying the early start date of any successor or violating a schedule constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is critical chain method(CCM)

A

Is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How buffers are used in critical chain method

A

It uses activities with durations without safety margin, logical relationships, and resources availability with statistically determined buffers composed of the aggregated safety margins of activities at specified points on the project schedule path to account for limited resources and project uncertainties

17
Q

What is critical chain

A

Resource constraint critical path is known as the critical chain

18
Q

What are the resource optimisation techniques?

A

Resource levelling

Resource Smoothing

19
Q

Difference between Resource levelling and Resource Smoothing

A

Resource levelling gives priority to ensure that the resources do not get over allocated to Tasks. This may result in critical path to get extended.

Resource Smoothing on the other hand only optimised resource usage to the point where critical path is not impacted.

20
Q

What are the modelling techniques?

A

What if analysis

Simulation techniques

21
Q

What is what-if analysis?

A

It is the process of evaluating scenarios in order to predict their effects on the project objectives.

A schedule network analysis is done on the schedule to compute the different scenarios such as delaying a major component delivery, extending a specific engineering component, or introducing external factors such as strike or a change in the permit process

22
Q

what is simulation

A

This involves calculating different sets of activity assumption, usually using probability distributions constructed from the three point estimates to account for uncertainty. The most common simulation technique is monte Carlso analysis, in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project

23
Q

What is schedule compression?

A

Is a technique used to shorten the project duration without reducing the project scope, in order to meet schedule constraints, imposed dates, or other schedule objectives.

24
Q

what are the schedule compession tecnuques?

A

1) Crashing- increase resources, overpayments, paying to expedite delivery to activities on the critical path.
2) Fast tracking - activities or phases normally done in sequence are done in parallel for atleast a portion of their duration.

25
Q

What are the outputs of develop schedule process?

A

Schedule Baseline: approved version of a schedule model that can be changed only through a change control procedure.

Project Schedule: