7.4 Control Costs Flashcards

1
Q

What is control costs process?

A

Process of monitoring the status of the project to update the project costs and managing changes to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the benefit of this process?

A

it provides the means to recognise variance from the plan in order to take corrective action and minimize risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does cost control invovle?

A

It involves analyzing the relationship between the consumption of project funds to the physical work being accomplished for such expenditures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How costs are controlled?

A

/influencing the factors that create changes to the authorized cost baseline
/ensuring that all changes are acted on in a timely manner
/managing the actual changes when they occur
/ensuring that cost expenditures do not exceed authorized funding by period, by WBS component, by activity, and in total for the project
/monitor work performance against funds expended
/preventing unapproved costs from being included in the reported costs or resource usage
/informing all stakeholders of approved changes and associated costs
/bringing expected cost overruns within acceptable limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the inputs to control costs process?

A

/project management plan-cost baseline, cost management plan

/project funding requirements - projected expenditure and anticipated liabilities

/work performance data-progress of activities, costs that have been authorised and incurred

/organisational process assets-Existing cost control-related policies, procedures and guidelines, tools and monitoring and reporting methods to be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How project management plan helps control costs?

A

/it contains cost baseline

/cost management plan that tell how costs are managed and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How project funding requirements help?

A

It contains projected expenditure and liabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How org process assets help

A

Contains formal / informal policies, procedures and guidelines to control costs

Cost control tools

Monitoring and reporting methods to be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what are the control costs tools and techniques?

A
/earned value management
/forecasting
/To-complete performance index
/Performance reviews
/project management software
/reserve analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is EVM (earned value management)?

A

It is a methodology that combines scope, schedule and resource measurements to assess project performance and progress. It integrates scope baseline with cost baseline along with the schedule baseline to form the performance measurement baseline which helps the project management team assess and measure project performance and progress for the duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 3 key dimensions developed and monitored by EVM for each work package and control account?

A

/Planned value (PV): Authorised budget allocated to scheduled work, not including management reserve. At a given time PV defines the physical work that should have been completed.

/Earned value (EV): It is the budget associated with the authorized work that has been completed. It is not the actual cost, but the planned cost for that piece of work.

/Actual Cost (AC): It is the reaslised cost incurred for the work performed on an activity during a specified time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is scheduled variance(SV) ?

A

It is a measure of schedule performance expressed as a difference between earned value (EV) and planned value (PV).
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is cost variance (CV)

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is SPI (Schedule Performance Index)?

A

SPI = EV/PV
SPI < 1 means behind schedule
SPI > 1 means ahead of schedule
since SPI is for the whole project, analysis to be done along the critical path to determine the impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Cost Performance Index(CPI)?

A

CPI=EV/AC

CPI > 1 indicates a cost underrun for work completed

CPI < 1 indicates a cost overrun for work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is EAC and how is it related to BAC?

A

EAC=Estimate at completion
BAC=Budget at completion

BAC is based on approved budget.
EAC is estimated cost at completion based on the current estimates

17
Q

How do we calculate EAC?

A

EAC = Actual Cost + Estimat to completion (ETC)

18
Q

What is ETC?

A

Estimate to Completion = Estimated cost to complete the remainder of the project

19
Q

What are the three common methods to calculate EAC?

A

1) EAC forecast for ETC work performed at the budgeted rate EAC = AC + (BAC- EV)
2) EAC forecast for ETC work performed at present CPI
EAC=BAC/CPI
3) EAC forecast for ETC work considering both CPI and SPI factors
EAC = AC + [(BAC - EV) / (CPI * SPI)]

20
Q

What is To Complete Performance Index?

A

Measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal.

TCPI=Cost to finish the outstanding work/remaining budget

21
Q

Equation for TCPI based on the BAC

A

(BAC-EV)

22
Q

What is to-complete performance index(TCPI)?

A

it is the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as =
Cost to finish the outstanding work/Remaining budget

23
Q

How Are Performance Reviews used as a tool/technique for cost control?

A

By comparing cost performance overtime, schedule activities or work packages overrunning and underrunning the budget, and estimated funds needed to complete work in progress.
When EVM is used, below information is determined as part of this:

Variance analysis

Trend Analysis

Earned value performance

24
Q

What is variance analysis?

A

It is the explanation (cause, impact and corrective actions) for cost, schedule and variance at completion variances.
An important aspect of project cost control includes determining the cause and degree of variance relative to the cost baseline and deciding whether corrective or preventive action is reuired

25
Q

What happens to range of acceptable variances as more work is accomplished?

A

It will tend to decrease

26
Q

What is trend analysis?

A

It examines project performance over time to determine if performance is improving or deteriorating

27
Q

How graphical analysis techniques are used ?

A

It is used for understanding performance to date and for comparison to future performance goals in the form of BAC Vs EAC and completion dates

28
Q

How reserve analysis is used for Const Control?

A

It is used to monitor status of contingency and management reserves for the project to determine if these reservers are still needed or if additional reserves need to be requested

29
Q

Outputs of Const Control Process

A

/Work performance information - SV,PV, CPI, SPI etc.
/Cost forecasts- Calculated EAC or bottom-up EAC
/Change Requests - Analysis of cost may result in change
/PM plan updates - cost baseline/cost mgmt plan
/Project Document Updates - activity cost estimates/basis of estimates
/Org proecss assets updates - causes of variances, corrective actions chosen and the reasons, Financial databases, Other type of lessons learned from project cost control