6.7 Control Schedule Flashcards

1
Q

What is control schedule process?

A

It is the process of monitoring the status of project activities to update project progress and to manage changes to the schedule baseline to achieve the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are any changes to the schedule baseline managed?

A

Changes to the project baseline can only be approved through the Perform Integrated Change Control process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Control Schedule process concerned with as a component of the Perform Integrated Change Control process?

A

/determining the current status of the project schedule
/influencing the factors that create schedule changes
/determining if the project schedule has changed
/managing the actual changes as they occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Control Schedule concerned with when agile approach is utilised?

A

/determining the current status of the project schedule by comparing the total amount of work delivered and accepted against the estimated work completed for the elapsed time cycle
/conducting retrospective reviews for correcting processes and improving, if required
/Re-prioritising the remaining work plan (backlog)
/determining the velocity per iteration
/determining that the project schedule has changed
/managing the actual changes as they occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the inputs to Control Schedule process?

A

/Project management plan: as it contains the schedule baseline and schedule management plan that describes how the schedule will be managed and controlled
/Project schedule - up to date. activities completed, started and updates having notations
/Work performance data - % completion, start, finish
/Project Calendars
/Schedule data
/Org process asset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the control schedule - tools and techniques?

A
/performance rviews
/project management software
/resource optimisation techniques
/modeling techniques
/leads and lags
/schedule compression
/scheduling tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the techniques used for Performance Reviews?

A

/Trend Analysis
/Critical Path Method
/critical chain method
/earned value management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is trend analysis?

A

Examines project performance over time to determine if performance is improving or deteriorating. Graphical analtysis techniqus are used to analyse performance to date and for comparison to future performance goals in the form of completion dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Relevance of CPM in Control Schedule process

A

Variance on the critical path will have a direct impact on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Relevance of CCM in Control Schedule process

A

Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date. Difference between buffer needed and buffer remaining can determine whether corrective action is appropriate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are important aspects of schedule control under earned value management?

A

/determine cause and degree of variance relative to the schedule baseline
/estimating the implications of those variances for future work to completion
/deciding whether corrective or preventive action is required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are Control Schedule outputs?

A

/Work Performance Info: The calculated SV and SPI time performance indicators for WBS components, in particular, the work packages and control accounts are documented and communicated to stakeholders
/Schedule Forecasts
/Change Requests
/Project Management Plan Updates: Schedule and Cost updates, Schedule Management plan updates
/Project Document Updates: Schedule Data, Project Schedule and Risk Register
/Organisational proecess assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly