PRINCE2 Processes Flashcards

1
Q

What are the PRINCE2 processes?

A

starting a project
initiating a project
directing a project
controlling a stage
managing a stage boundary
managing product delivery
closing a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of Managing Product Delivery?

A

To control the link between the PM and Team Manager(s) by agreeing the requirements for ACCEPTANCE, EXECUTION and DELIVERY.

Team Managers coordinate this work, and can be internal or external to the customer’s organisation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of Controlling a Stage?

A

ASSIGN work to be done
Monitor the work
Deal with ISSUES
REPORT progress to Project Board
Take corrective actions to ensure the management stage remains within TOLERANCE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of Initiating a Project?

A

To establish solid FOUNDATIONS for the project, enabling the organisation to understand the work required to deliver the products before committing to a significant SPEND

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of Managing a Stage Boundary?

A

To enable the PM to provide the Project Board with sufficient information to REVIEW the success of the current management stage, APPROVE the next stage plan, review the updated project plan, confirm BUSINESS JUSTIFICATION and acceptability of the RISKS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of Closing a Project?

A

To provide a fixed point at which ACCEPTANCE for the project product is confirmed
To recognise that OBJECTIVES set out in the PID (or approved changes to them) have been achieved, or that the project has nothing more to contribute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of Directing a Project?

A

To enable the Project Board to be ACCOUNTABLE for the project’s success by making key DECISIONS and exercising overall control while DELEGATING day-to-day management to the PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of Starting Up a Project?

A

To ensure the pre-requisites for Initiating a Project are ihn place by answering the question: Do we have a VIABLE and WORTHWHILE project?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly