4.0 Directing a Project Flashcards

1
Q

What is the purpose of starting up a project?

A

To ensure the pre-requisites for Initiating a Project are in place by answering the question: Do we have a viable and worthwhile project?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of Initiating a Project?

A

To establish solid foundations for the project, enabling the organisation to understand the work that needs to be done to deliver the project’s products before committing to a signifiant spend

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of Controlling a Stage?

A
  • to assign and monitor work to be done;
  • deal with issues;
  • report progress to the Project Board;
  • take corrective actions to ensure the management stage remains within tolerance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of Managing Product Delivery?

A

To control the link between the PM and the Team Manager(s) by agreeing the requirements for ACCEPTANCE, EXECUTION and DELIVERY

Team Manager(s) coordinate this work, and can be internal or external to the customer’s organisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of Closing a Project?

A

To provide a fixed point at which acceptance for the project product is confirmed, and to recognise that objectives set out in the original PID have been achieved (or approved changes to the objectives have been achieved), or that the project has nothing more to contribute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of Directing a Project?

A

To enable the Project Board to be accountable for the project’s success by making key decisions and exercising overall control while delegating day-to-day management of the project to the PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 5 main decisions of Directing a Project?

A
  1. Authorise initiation
  2. Authorise the project
  3. Authorise a Stage/Exception Plan
  4. Give ad-hoc direction (continual activity where decisions are made about progress, issues, risks & exceptions)
  5. Authorise project closure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 7 main objectives for the Directing a Project process?

A
  • Authority to initiate the project
  • Authority to deliver the project’s products
  • Management direction & control throughout the project’s lifecycle
  • The project remains viable
  • Corporate, programme management or the customer has an interface to the project
  • Authority to close the project
  • Plans for realising the post-project benefits are managed and reviewed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Objectives: Authority to initiate the project

A

Decision Point 1 (Authorise Initiation) is where the Project Board, immediately after completion of SU, uses the Project Brief to authorise initiation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Objectives: Authority to deliver the project’s products

A

Decision Point 2 (Authorise the Project) is where the Project Board, immediately after IP, uses the PID to authorise initiation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Objectives: Management direction & control throughout the project’s lifecycle

A

Decision Point 4 (Ad Hoc Direction) is where the Project Board, with links to the PM’s activities in Controlling a Stage, ensures it is in overall control between stages, whilst delegating day-to-day management to the PM

Decision Point 3 (Authorise Stage/Exception) is where the Project Board, immediately after Managing a Stage Boundary at an End Stage Assessment, uses the End Stage Report, next Stage Plan and updated PID to authorise continuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Objectives: The project remains viable

A

This relates to all decisions being taken in the context of any impact on the Business Case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Objectives: Corporate, programme management or the customer has an interface to the project

A

This emphasises that the link to corporate or any higher programme is through the Project Board (not the Project Manager)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Objectives: Authority to close the project

A

Decision Point 5 (Authorise Project Closure), with links to Closing a Project, is where the Project Board authorise closure of the project based on formal acceptance of the project product and its ongoing sustainability by the Project Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Objectives: Plans for realising the post-project benefits are managed and reviewed

A

This indicates that the execution of the Benefits Review Plan is by the Executive and Senior User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The requirement for the Project Board to act as a communications channel, and how it is going to do it, should be documented in…

A

the Communications Management Approach

17
Q

Decision Point 1: Authorise Initiation

A

Projects take time and cost money to initiate, so the activities for initiation should be planned, monitored and controlled. The Project Board activity to authorise initiation ensures that such investment is worthwhile.

18
Q

Decision Point 2: Authorise the Project

A

This activity will be triggered by a request from the PM for authorisation to deliver the project, and may be undertaken in parallel with authorising a Stage or Exception Plan.

19
Q

Decision Point 3: Authorise a Stage or Exception Plan

A

The Project Board authorises a management stage by reviewing the performance of the current stage and approving the Stage Plan for the next stage.

(Approval of Stage Plans occurs at the end of every management stage except for the last one)

20
Q

Decision Point 4: Give Ad Hoc Direction

A

Project Board members may offer informal guidance or respond to requests for advice at any time during a project.

21
Q

Decision Point 5: Authorise Project Closure

A

There must be a point when the objectives in the original and current versions of the PID and Project Plan are assessed in order to understand:
- whether the objectives have been achieved
- how the project has deviated from its initial bias
- that the project has nothing more to contribute

22
Q

Activities: DP1 Authorise Initiation

A
  • Project Board approves the Project Brief
  • Project Board approves the Stage Plan (Initiation)
23
Q

Activities: DP2 Authorise the Project

A
  • Project Board / Assurance reviews the lessons log
  • Project Board approves the PID
  • Project Board approves the Benefits Management Approach
24
Q

Activities: DP3 Authorise a Stage/Exception Plan

A
  • Project Board confirmed Specialist Products Approval
  • Project Board approves End Stage Report
  • PM distributes lessons report
  • Project Board approves Follow-on action recommendations
  • Project Board approves Stage Plan
  • Project Board approves Exception Plan
  • Project Board approves updated PID
  • Project Board approves updated Benefits Management Approach
25
Q

Activities: DP4 Ad Hoc Direction

A
  • Project Board reviews Highlight Report
  • Project Board responds to Exception Report
  • Project Board raises new issue
26
Q

Activities: DP5 Authorise Project Closure

A
  • Project Board approves End Project Report
  • Project Board distributes lessons report
  • Project Board distributes follow-on action recommendations
  • Project Board confirms updated Business Case
  • Project Board approves updated Benefits Management Approach
27
Q

Which theme do the Directing a Project decision points relate to?

A

the progress theme

28
Q

Which product is the decision to Authorise Initiation based upon?

A

Project Brief (with acceptance criteria and outline business case, and initiation stage plan)

29
Q

Which product is the decision to Authorise the Project based upon?

A

PID

30
Q

Which products is the decision to Authorise a Stage or Exception Plan based upon?

A

End Stage Report
next Stage Plan
updated PID

31
Q

Which product is the decision to Authorise Project Closure based upon?

A

end project report

32
Q

What is the decision to Give Ad hoc Direction based upon?

A

on receipt of highlights, issues and exceptions

33
Q

What products does the Directing a Project process produce?

A

None - the Project Board are mainly responsible for reviewing and approving the products produced in different processes

34
Q

When initiation is authorised, the board must issue…

A

an initiation notification