13.0 Managing a Stage Boundary Flashcards

1
Q

What is the purpose of the Managing a Stage Boundary process?

A

To enable the Project Manager to provide the Project Board with sufficient information to:

  • Review the success of the current management stage
  • Approve the next stage plan
  • Review the updated project plan
  • Confirm continued business justification & acceptability of the risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of the Managing a Stage Boundary process in an exception situation?

A

To ensure that the output from re-planning is an Exception Plan which is submitted for Project Board approval in the same way that a Stage Plan is submitted for approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When should the Managing a Stage Boundary process be executed?

A

at or close to the end of each management stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activities within Managing a Stage Boundary process

A
  • Plan the next management stage
  • Update the Project Plan
  • Update the business case
  • Report the end of the management stage
  • Produce an Exception Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who does what in Reporting Management Stage End?

A
  • Project Manager creates End Stage Report
  • Project Manager creates lessons report
  • Project Manager creates follow-on action recommendations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who does what in Updating the Business Case?

A
  • Project Manager updates Business Case
  • Project Manager updates Benefits Management Approach
  • Project Manager updates Risk Register
  • Project Manager updates Issue Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who does what in Producing an exception plan?

A
  • Project Manager updates PID
  • Project Manager creates Exception Plan
  • Project Support updates/creates Configuration Item Records
  • Project Manager updates Risk Register
  • Project Manager updates Issue Register
  • Project Support updates Quality Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who does what in Updating the Project Plan?

A
  • Project Manager updates Project Plan
  • Project Manager updates Issue Register
  • Project Manager updates Risk Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who does what in Planning the next management stage?

A
  • Project Manager updates PID
  • Project Manager creates Stage Plan
  • Project Manager creates Configuration Item Records
  • Project Manager updates Risk Register
  • Project Manager updates Issue Register
  • Project Support updates Quality Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the main products of the Managing a Stage Boundary process?

A
  • Stage Plan
  • Product descriptions
  • End Stage Report
  • Lessons Log
  • Exception Plan