11.0 Managing Product Delivery Flashcards

1
Q

What is the purpose of managing product delivery?

A

To control the link (the work package) between the Project Manager and the Team Managers by agreeing the requirements for ACCEPTANCE, EXECUTION and DELIVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Objectives of Managing Product Delivery

A
  • work on products is authorised and agreed
  • ensure supplier-side clarity on ‘what’ is to be produced and expected effort, cost and time
  • deliver products to expectations and within tolerance
  • provide accurate progress information to the Project Manager at an agreed frequency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Once the work package is agreed, the Team Manager sets about getting their team to…

A
  • create products
  • test products
  • get the products approved by management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

3 elements of managing product delivery

A
  1. ACCEPTING a work package
  2. EXECUTING a work package
  3. DELIVERING a work package
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Before a work package is allocated to a team, there should be agreement between ___________ and ___________ as to what is to be delivered.

A

the Project Manager

the Team Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

As soon as work package tolerances are forecast to be exceeded, the Team Manager should…

A

raise an issue to the Project Manager, who will then decide upon a course of action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who should be notified when a work package is completed?

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who does what in accepting a work package?

A
  • Team Manager creates Team Plans
  • Project Manager/Support updates Risk Register
  • Project Support updates Quality Register
  • Project Manager approves Work Package
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who does what in executing a work package?

A
  • Team Manager creates specialist products
  • Project Support updates Quality Register
  • Team Manager updates Team Plan
  • Team Manager creates Checkpoint Report
  • Project Manager / Support updates Issue Register
  • Project Manager / Support updates Risk Register
  • Team Manager obtains Approval Records
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who does what in delivering a work package?

A
  • Team Manager updates Work Package

- Team Manager updates Team Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are Team Managers responsible for?

A

The CREATION, TESTING and gaining of management APPROVAL of products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which products are produced in Managing Product Delivery?

A
  • Team Plan

- Checkpoint Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the Team Plan include?

A

Components in any format commensurate with the complexity of the work package, with views ranging from a simple list of accountabilities, products, activities and dates to Gantt charts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When should the Team Plan be developed?

A

At the same time as the Stage Plan, not waiting for the work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly