Q
What did you advise could be the issues with accepting Option 2 in your case Study?
A
- Client is seriously programme driven.
- Client issues lots of changes. EOTs would be plentiful.
- Adversarial relationship
- Client forced to take partial possession and have difficult mobilisation period
- PP would be an EOT and RM to Contractor
- Overlapping work areas
- Fundamentally, it would be the Client’s problem…
2
Q
Can you give an example of when you have advised your client about Sectional Completion or Partial Possession?
A
- Yes on the Hinckley project, Client wanted to award Practical Completion for political reasons with a list of snags that were not in any way de-minimis.
- Works not complete, and certainly not a snag.
- Partial possession should be taken to retain LDs and retention on uncompleted works.
- Insurance of the area would get extremely complicated.