What did you advise could be the issues with accepting Option 2 in your case Study?

A
  • Client is seriously programme driven.
  • Client issues lots of changes. EOTs would be plentiful.
  • Adversarial relationship
  • Client forced to take partial possession and have difficult mobilisation period
  • PP would be an EOT and RM to Contractor
  • Overlapping work areas
  • Fundamentally, it would be the Client’s problem…
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you give an example of when you have advised your client about Sectional Completion or Partial Possession?

A
  • Yes on the Hinckley project, Client wanted to award Practical Completion for political reasons with a list of snags that were not in any way de-minimis.
  • Works not complete, and certainly not a snag.
  • Partial possession should be taken to retain LDs and retention on uncompleted works.
  • Insurance of the area would get extremely complicated.