Case Study Questions Flashcards

1
Q

What RIBA Deliverables were in place when you were appointed? What did you create?

A

RIBA 1 deliverables were:

  • Outline programme (high level)
  • Template Design pack
  • ‘Test Fit’
  • Due Diligence Report
  • Detailed Client Brief
  • High Level Project Brief

I created:

  • Project Execution Plan
  • Master schedule
  • RACI for Designers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Was it a LOI? What are the T&T procedures for LOIs?

A
  • Not to draft them under any circumstances
  • Advise the client clearly on all the risks and benefits and to obtain confirmation that the client understands the principles
  • Ampleforth Abbey case
  • However this was a separate contract, written by their lawyers, and based on a principle that the client had used before for early ground works.
  • Linked to main contract so that both would be signed together to bind them
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why was the DCI incompatible? Give me examples

A
  • It didn’t align to the subcontract procurement process. There was no provision for nominated contractors.
  • It claimed no cost impact but didn’t consider costs to the Contractor to facilitate in terms of money or programme.
  • Wasn’t clear who managed the design in the business and when it started or how it was procured.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between a vision and a goal?

A

Vision - How and where you see yourself in the future

Goal - Specific target on the way to achieving your vision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What advice did you provide the Sustainability team?

A
  • Principle around Nominated Subcontractors
  • Cost of design change over time curve
  • Design integration with PD and CDM
  • ‘Ensure’ implies contractual responsibility
  • If subcontracting they wouldn’t have to hand over the area back to the client for their own supplier to then work in
  • Principle of management costs associated with subcontractors; reviewing RAMs, site management, Principal Contractor role etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What other ideas were investigated at the workshop?

A
  • Subcontractor incentivisation (no guarantee of improvement)
  • Additional piling/groundworks resource (acceleration) (no rigs available)
  • Sub-dividing the Sectional Completion areas
  • Night time working
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you go about the workshop?

A
  • Set out the purpose of the workshop in a briefing note
  • Encouraged involvement from all parties
  • Chaired discussion and took minutes
  • Issued minutes and actions and followed up with Client in terms of reporting
  • Asked Developer to formalise their programme to show that it worked
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What process did you follow for your Options Appraisal?

A
  • Scope and audience
  • Problem statement and key objective
  • Explanation of each option with supporting information such as cost, risks, advantages and disadvantages
  • Recommendation
  • Proposed action plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the steel was critical path on the construction programme why did you bother identifying anything else?

A
  • Assumed we could accelerate the steelwork and some element prior to it
  • Programme wide procurement decision to take steel from another supplier
  • Getting out of the ground more
  • Discussed things post-steelwork too
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How long was the committee date delayed for? From when until when? What was the original and revised PC Date?

A
  • 9 weeks from the 6th Jan to 10th March

- 29th July and then 30th September

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was the original and impacted planning approval date?

A
  • 27th Jan and 31st March
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What was the original and impacted JR Expiry date?

A
  • 24th March and 26th May
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What as the original and impacted unconditional date?

A
  • 25th March and 27th May
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What was the original and impacted PC Date?

A
  • 29th July and 30th September
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What was the final PC date?

A
  • 26th August 2022
How well did you know this?
1
Not at all
2
3
4
5
Perfectly