2 - Project Finance Flashcards

1
Q

What are the different types of Cost Report?

A

1) Elemental
2) Construction
3) Project
4) Programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain an S-Curve

A
  • Plots COWD against time
  • As you go through the project, an S-Curve is formed
  • Can analyse project performance by reviewing if you are in front of or behind the curve
  • HOWEVER - It can mean that maybe the costs were front loaded, or that the works are over-priced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Cost Control?

A

The processes and procedures to align and manage cost in line with the Cost Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Cost Plan?

A

The overarching plan of the project costs over time. An evolving document that grows in accuracy and scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What informs the early stages of a cost plan?

A
  • Initial appraisal through feasibility study

- Ballpark/OOM estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What informs the middle stage of a cost plan?

A
  • PTE

- Quants taken from design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What informs the final stages of a cost plan?

A
  • CSA and Contract Sum

- Final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Under NEC, what is Defined Cost?

A

The costs permitted under the Contract that are incurred/expended by the Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Schedule of Cost Components?

A

The set list of categories of Defined Costs that form the total of the prices. These are:

  1. People
  2. Equipment
  3. Plant and materials
  4. Charges
  5. Manufacture
  6. Design
  7. Insurance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When are the Shorter Schedule of Cost Components used?

A

On options A and B for CEs. Can be used on C&D if the PM agrees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are Disallowed costs?

A

Costs that are incurred by the Contractor that they are not entitled to payment such as:

  • Amounts not justified by records
  • Amounts paid for something else not part of the project
  • Errors or mistakes in payment to others
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What cost measurement methods are there?

A
  • NRM1 - Order of cost planning for building works
  • NRM2 - Detailed measurement of buildings works
  • NRM3 - Order of cost and measurement of Maintenance Works
  • ICMS - International Construction Measurement Standards
  • RMM - Rail Method of Measurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was the Standard Method of Measurement replaced by?

A

NRM2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What affects an Outturn Cost?

A

Fixed costs - The works undertaken

Variable - Changes, prov sums etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Price of Work Done to Date?

A

Defined cost the contractor will have spent before the next assessment date, which includes CEs, plus their fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly