2 - Project Finance Flashcards
What are the different types of Cost Report?
1) Elemental
2) Construction
3) Project
4) Programme
Explain an S-Curve
- Plots COWD against time
- As you go through the project, an S-Curve is formed
- Can analyse project performance by reviewing if you are in front of or behind the curve
- HOWEVER - It can mean that maybe the costs were front loaded, or that the works are over-priced.
What is Cost Control?
The processes and procedures to align and manage cost in line with the Cost Plan
What is a Cost Plan?
The overarching plan of the project costs over time. An evolving document that grows in accuracy and scope.
What informs the early stages of a cost plan?
- Initial appraisal through feasibility study
- Ballpark/OOM estimates
What informs the middle stage of a cost plan?
- PTE
- Quants taken from design
What informs the final stages of a cost plan?
- CSA and Contract Sum
- Final account
Under NEC, what is Defined Cost?
The costs permitted under the Contract that are incurred/expended by the Contractor
What is the Schedule of Cost Components?
The set list of categories of Defined Costs that form the total of the prices. These are:
- People
- Equipment
- Plant and materials
- Charges
- Manufacture
- Design
- Insurance
When are the Shorter Schedule of Cost Components used?
On options A and B for CEs. Can be used on C&D if the PM agrees.
What are Disallowed costs?
Costs that are incurred by the Contractor that they are not entitled to payment such as:
- Amounts not justified by records
- Amounts paid for something else not part of the project
- Errors or mistakes in payment to others
What cost measurement methods are there?
- NRM1 - Order of cost planning for building works
- NRM2 - Detailed measurement of buildings works
- NRM3 - Order of cost and measurement of Maintenance Works
- ICMS - International Construction Measurement Standards
- RMM - Rail Method of Measurement
What was the Standard Method of Measurement replaced by?
NRM2
What affects an Outturn Cost?
Fixed costs - The works undertaken
Variable - Changes, prov sums etc.
What is the Price of Work Done to Date?
Defined cost the contractor will have spent before the next assessment date, which includes CEs, plus their fee