3 - Programming and Planning Flashcards

1
Q

What is the difference between Total and Free Float?

A
  • Total float is the amount of time an activity can be delayed before affecting the end date
  • Free float is the amount of time an activity can be delayed before affected a subsequent activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Critical Path?

A
  • The longest duration through the activity network, which in turn defines the shortest time the project can be completed in.
  • There is no float on the CP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain Earned Value

A

Earned Value looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the SPI calculation

A
  • Earned Value divided by Planned Value e.g.

100m wall, £1,000 per metre, 100 days duration. At day 10 there is 20m of wall complete.

20 divided by 10 = 2.

Greater than 1.0 is good, less is bad.

Can then apply this factor to the end date to get a forecast completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain the CPI calculation

A
  • Earned Value divided by Actual Cost e.g.

100m wall, £1,000 per metre, 100 days duration. At day 10 there is 5m of wall complete, but it’s cost £10,000:

5000 divided by 10,000 = 0.5

Greater than 1.0 is good, less is bad

Divided the total cost by 0.5 to get EAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What kinds of Delay analysis are you aware of?

A

Split in to two key camps: proactive and retrospective.

  • Time impact analysis - do it as you go. Drop in the change.
  • Time Slice Window - Retrospectively split your programme in to time windows and drop in the impact sequentially. Effectively a retrospective NEC approach.
  • Collapsed As Built - Take the as-built and subtract the delay out of it

All require good records and programme data..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you create a programme?

A
  • Scope of programme
  • WBS
  • Plug in constraints
  • Fill in what I know
  • Consult wider team
  • Add risk and opportunity
  • Run analysis of scenarios
  • Identify the CP
  • Identify assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How can you show progress on a programme?

A
  • Drop line
  • % Complete metrics
  • Jagged drop line
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is time at large?

A

When the EOT mechanism is broken and unenforceable meaning Completion is effectively whatever it ends up being. Removes obligation to pay LADs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some alternatives to a Gantt Chart?

A
  • Network Diagrams
  • WBS
  • Kanban board/task list
  • Sprint cycles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between resource levelling and resource smoothing?

A

Both are used to avoid peaks and troughs, but:

Levelling = when resources are constrained, what is the programme going to be?

Smoothing = when time is constrained, can resources be smoothed out to achieve the end date? I.e. delay some tasks to get the CP done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you explain a time where the programme was impacted?

A
  • North Pole train standing
  • Temple Mills change of access arrangements
  • Planning delay to Basingstoke
How well did you know this?
1
Not at all
2
3
4
5
Perfectly