lessons learned 9-8-19 Flashcards

1
Q

Tuckman’s ladder: the stage where team members meet and learn about the project and their formal roles and respnsibilities

A

Forming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tuckman’s ladder: the stage where team members beging to address the project work, technical decision and project management approach

A

Storming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tuckman’s ladder: the stage where team functions as well-organized unit and work through issues smoothly and effectlively

A

Performing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tuckman’s ladder: the stage where team members are adjusting the work habits and behaviors to support the team as they learn to trust each other

A

Norming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The resource management plan can be divided into two management plans. What are they:

A

The team management plan and the physical resource management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

This process involvies providing information as well as allowing stakeholders to request additional information and clarification as needed. This includes details on how to escalate their concerns.

A

Communications management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project managers identify key deliverables based on?

A

The business requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where would you find the contract change control system?

A

In your company’s EEF’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In an adaptive lifecycle, what 3 process are repeated for each iteration?

A

Collect requirements, Define Scope, Create WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly