EVM definitions Flashcards

1
Q

Planned value (PV)

A

What the project should be worth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned value (EV)

A

What the project is worth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual cost (AC)

A

What the project has spent so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

What the project budget is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost variance (CV)

A

The difference between earned value and the actual costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule variance (SV)

A

The difference between earned value and planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at Completion (VAC)

A

Projection of being over or under budget based on current performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

Shows overall cost efficiency on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index (SPI)

A

Shows overall schedule adherence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

A

Forecasts final project costs based on current performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Complete

A

Predict how much more the remainder of the project will costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI to complete performance index (Utilizing BAC)

A

Predicts the likelihood of reaching BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPI to complete performance index (Utilizing EAC)

A

Predicts the likelihood of reaching EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What the project should be worth.

A

Planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What the project is worth

A

Earned value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What the project has spent so far

A

Actual cost (AC)

17
Q

What the project budget is

A

Budget at Completion (BAC

18
Q

The difference between earned value and the actual costs

A

Cost variance (CV)

19
Q

The difference between earned value and planned value

A

Schedule variance (SV)

20
Q

Projection of being over or under budget based on current performance

A

Variance at Completion (VAC)

21
Q

Shows overall cost efficiency on the project

A

Cost Performance Index (CPI)

22
Q

Shows overall schedule adherence

A

Schedule Performance Index (SPI)

23
Q

Forecasts final project costs based on current performance

A

Estimate at Completion (EAC)

24
Q

Predict how much more the remainder of the project will costs

A

Estimate to Complete

25
Q

Predicts the likelihood of reaching BAC

A

TCPI to complete performance index (Utilizing BA

26
Q

Predicts the likelihood of reaching EAC

A

TCPI to complete performance index (Utilizing EAC)