EVM definitions Flashcards

1
Q

Planned value (PV)

A

What the project should be worth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned value (EV)

A

What the project is worth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual cost (AC)

A

What the project has spent so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

What the project budget is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost variance (CV)

A

The difference between earned value and the actual costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule variance (SV)

A

The difference between earned value and planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at Completion (VAC)

A

Projection of being over or under budget based on current performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

Shows overall cost efficiency on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index (SPI)

A

Shows overall schedule adherence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

A

Forecasts final project costs based on current performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Complete

A

Predict how much more the remainder of the project will costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI to complete performance index (Utilizing BAC)

A

Predicts the likelihood of reaching BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPI to complete performance index (Utilizing EAC)

A

Predicts the likelihood of reaching EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What the project should be worth.

A

Planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What the project is worth

A

Earned value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What the project has spent so far

A

Actual cost (AC)

17
Q

What the project budget is

A

Budget at Completion (BAC

18
Q

The difference between earned value and the actual costs

A

Cost variance (CV)

19
Q

The difference between earned value and planned value

A

Schedule variance (SV)

20
Q

Projection of being over or under budget based on current performance

A

Variance at Completion (VAC)

21
Q

Shows overall cost efficiency on the project

A

Cost Performance Index (CPI)

22
Q

Shows overall schedule adherence

A

Schedule Performance Index (SPI)

23
Q

Forecasts final project costs based on current performance

A

Estimate at Completion (EAC)

24
Q

Predict how much more the remainder of the project will costs

A

Estimate to Complete

25
Predicts the likelihood of reaching BAC
TCPI to complete performance index (Utilizing BA
26
Predicts the likelihood of reaching EAC
TCPI to complete performance index (Utilizing EAC)