EVM formulas Flashcards

1
Q

Earned value (EV)

A

Percent complete X BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost variance (CV)

A

EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule variance (SV)

A

EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variance at Completion (VAC)

A

BAC-EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Performance Index (CPI)

A

EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index (SPI)

A

EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion (EAC)

Standard formula

A

BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate at Completion (EAC)

Future work at planned costs formula

A

AC + BAC – EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

Initial costs estimates flawed

A

AC + Estimate for

remainder of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

CPI and SPI affect the remainder of the project

A

AC + [BAC-EV/(CPI x SPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Complete

A

EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI to complete performance index

Utilizing BAC

A

(BAC-EV)/(BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPI to complete performance index

Utilizing EAC

A

(BAC-EV)/(EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly