EVM formulas Flashcards
Earned value (EV)
Percent complete X BAC
Cost variance (CV)
EV-AC
Schedule variance (SV)
EV-PV
Variance at Completion (VAC)
BAC-EAC
Cost Performance Index (CPI)
EV/AC
Schedule Performance Index (SPI)
EV/PV
Estimate at Completion (EAC)
Standard formula
BAC/CPI
Estimate at Completion (EAC)
Future work at planned costs formula
AC + BAC – EV
Estimate at Completion (EAC)
Initial costs estimates flawed
AC + Estimate for
remainder of project
Estimate at Completion (EAC)
CPI and SPI affect the remainder of the project
AC + [BAC-EV/(CPI x SPI)]
Estimate to Complete
EAC-AC
TCPI to complete performance index
Utilizing BAC
(BAC-EV)/(BAC-AC)
TCPI to complete performance index
Utilizing EAC
(BAC-EV)/(EAC-AC)