10.3b - Network Analysis Flashcards

1
Q

Critical path analysis definition

A

A project analysis and planning method that allows a project to be completed in the shortest possible time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What information is needed for CPA to be carried out?

A
  • A list of activities required to complete the project
  • The duration that each activity will take to completion
  • The dependencies between activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does CPA calculate?

A
  • The shortest path of planned activities to the end of the project
  • Earliest and last time that each activity can start and finish without making the project longer
  • Which activities are critical and which have total float
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical activity definition

A

An activity that is on the shortest path to project completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Total float definition

A

When an activity can be delayed without making the project longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Node definition

A

A circle that represents a point in time where an activity is started or finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How can you quickly tell if a node is on the critical path?

A

The EST and LFT will be the same

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EST definition

A

The earliest start time that the activity can commence based on the completion of the previous activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

LFT definition

A

The latest finish time by which the previous activity must be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When two activities meet, will the next activity’s EST be the higher or lower figure?

A

Higher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When two activities meet, will the previous activities LFT be the higher or lower figure?

A

Lower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly