Track Safety: Rule 920 Working At Level Crossings Flashcards

1
Q

What must the RPO arrange when planned work may affect the approach track circuits of level crossings?

A
  • Manually control the level crossing
  • Have them disconnected by signals personnel
  • Have them remotely controlled by TC
  • This must be notified on a DIB or special bulletin
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What 4 things must the RPO ensure that each level crossing warning system is?

A
  • Operated by trained personnel
  • Managed using either manual or automatic operation, for train movements
  • Restored to normal operation at the completion of planned work and this is certified to TC
  • Unplanned use of manual control does not require notice by bulletins and will be arranged with the train controller as required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens when a level crossing has been disconnected?

A
  • A 10km/h speed restriction must be placed over the level crossing for the duration the alarms are disconnected, except when no train movements are planned.
  • Notification if the speed restriction will be included in the access providers speed restriction system or bulletin.