Tom's questions - SoE Flashcards

1
Q

Can you give an example of a gift you would need to record in a company register, and what you would need to record?

A

Any gift or offer of hospitality above a nominal value of £15 should be recorded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is it important to undertake conflict of interest checks.

A

Carrying of CoI checks is professional due diligence; an undisclosed conflict of interest could call into question the impartiality of the work carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type and/or age of building would you associate with RAAC.

A

I suspect RAAC in local authority built buildings such as schools, hospitals, colleges, social housing and fire stations built between 1950 and 2000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How could you manage a conflict of interest if it arose?

A

Depending on the conflict, if it is deemed to be manageable, this can be done by being open with all parties about the conflict and receiving written.

If the conflict is with the company such as working for two rival firms, the projects could be covered by use of a NDA and internal management such as keeping the projects in separate offices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do you understand by the term ‘non-intrusive’ inspection, and what is the importance of identifying this as part of your appointment?

A

Non-intrusive means that any concealed or covered areas will be outside the survey’s scope. And further opening up would be required before reinspection.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What would you expect to include in a fee draw?

A

The total anticipated fee, the contract value of a percentage-based fee, and a schedule of expected invoicing amounts. I also include details of invoices sent and if they are paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of a fee draw?

A

A fee draw can help project managers to plan their income and invoices. and it clearly sets out what is remaining to be invoiced.

It can also be shared with the client so they can plan their cash flow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of a cash-flow forecast and why is it important?

A

A cash flow forecast helps to manage finances, insuring they have enough cash to cover outgoings over a set period of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is it important to identify project stakeholders and manage their expectations?

A

Identifying the relevent stakeholders makes it more likely the project will successfully meet the needs of the people who will use the building.

stakeholders whos expectations are suitably managed will be less inclined to complain or be disappointed in a service if it does not match what they ere expecting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What would you include typically in a well-defined fee proposal?

A

a Fee proposal should inculde;

  • a outline of the client request and our understanding of their needs
  • The property it concerns
  • Our reccomended services
  • exclusions, limitations and caveats
  • the terms and conditions
  • the proposed fee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why would you obtain a record of appointment from the client?

A

-a written confirmation of appointment is the acceptance of the terms of business and the proposed fee

  • having a record can help with disputes, such as the client claiming you have caused a delay when they did not formally appoint you until late
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In your example of Ledbury market House, are there any risks of providing advice to a client without an appointment agreement? What action would you take?

A

Providing professional advice without an appointment still creates a duty of care, and negligent advice could result in a claim.

by keeping advice broad and generic, not specifying that the advice given is not to be relied on or acted upon without liability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In your Franks Lane flood reinstatement works project, what did you include in your weekly update report?

A

The weekly update was only a short email rather than a report, that would cover the current project programme and where we were up to and set out any information required from the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In our industry where there is a lot of technical detail language, why is it important in some circumstances to use plain language?

A

When talking to people from outside the industry, technical jargon can be a barrier to clear communication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you give an example of limitations you might include in a fee proposal?

A

Limitations might include that only high-level areas safely accessible from a three-meter ladder will be inspected, and unboarded roof voids will have a ‘head and shoulders’ inspection only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What different formats of reports might you use in different circumstances?

A

The format of report is dictated by the clients needs. When under taking PPM surveys on a portfolio of buildings a lengthy written report for each building could be information overload for a client. A simple photographic report with cost data is more suited to the level of detail required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In your Fire Service Training Centre project, what do you mean by the term ‘real-time’ when assisting stakeholders to visualise proposed layouts?

A

During the in-person meeting I brought up AutoCAD on my laptop and cast it onto the big screen. Using pre-drawn shapes indicating rooms I was able to move these around on the screen to show different suggestions from the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When undertaking surveys of domestic properties, what risks might there be to consider and how do you manage them? What action / precautions do you take? What guidance is available to assist you?

A

During surveys at domestic properties there are various risks I might encounter;

-The tenants/ home owners are unknown to me - They may be vunerable, or have issues such as drug/ alcohol abuse
- The properties could be in poor condition - there may be trip/ fall hazards as well as mould spores
- there may be dogs at the address

I use the RICS surveying safety guidance and my company’s internal health and safety guidance. During lone working I make sure a manager or, at minimum, another colleague knows where I am and when I expect to leave.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Can you explain what was included in your ‘Quality Monitoring’ role for Norham Gardens? Can you give some examples of what you identified and included within your reports?

A

My role at Norham gardens was to act on behalf of the client to identify risks to the project programme or quality as it was a design and build project.

for instance, I identified that the CLT moisture management plan specified that weep holes should be included in the roof structure to provide an early warning system for roof leaks. However, it also specified that these were taped over during the air tightness testing, which I queried as this would give a false reading on the air tightness and building performance (Passivhaus).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

In respect of your role as a Building Surveyor, what are the Principal ‘regulations’ and considerations under the Building Safety Act?

A

it has introduced new duty holders similar to those of the CDM regulations, these apply to almost all building projects:
- principal designer must be appointed in writing before construction begins
-Principle Contractor
- the Client

The BRPD’s role is to audit the design process and challenge design changes to ensure compliance with building regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the hazards associated with entering basements and roof voids?

A

Basements and roof voids, can both be confined spaces where I could encounter hazards such as vermin faeces, asbestos, unstable surfaces (put foot through a ceiling), low lighting levels, fall hazards at access hatches. ladders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What regulations cover these activities? (entering basements and roof voids)

A

The health and saftey at work act
The working at height regulations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

In using the drone for Rectors Lodge, what did you assess when compiling a Flight Plan? What goes into a Flight Plan?

A

The flight plan looks at the site location, potential risks in the area and mitigation for those risks or restricted flying areas, the details of the nearby hospital, and where the pilots will locate themselves during the flight and the planned path of the flight.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Whose responsibility is it to provide pre-construction information under the CDM regulations?

A

This is a duty of the client. However, it is typically passed with an agreement to the principal designer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

In your Lobelia Road project, what did you identify for the PCI?

A

The details of the PD, PM and client

I identified that the project site had limited space for site set-up and being on a residential street consideration would need to be given to vehicle access and parking

I included the CCTV drainage survey and refurbishment and demolition survey

The requirements of the health and safety file to be provided by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What must be included in PCI?

A

a description of the site and the works including access requirements
a risk assessment of the site
a designer risk assessment
details of any known hazards materials on-site, or site specific hazards
client requirements for management of the works such as permits to work
Survey reports
Requirements of the health and safety file

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Why is it important to issue clear invoices to clients?

A

Confusion over what an invoice covers or has already been paid can cause payment delays and worry for the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are the main things you would include in a Business Plan?

A
  • Overview what the bussiness plan aims to achieve
    -the strategy for reaching the aims and analysis of the situation (swot or pestle)
    -end goal and road map what are the KPIs, timescales, review periods and intermediate goals.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

How would you monitor the effectiveness of a business plan

A

By setting targets or KPI’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What do you consider to be the main influences currently on construction sector risks/opportunities?

A

Risks:
- High construction costs continue
- Lack of labour and skills

Opportunities:
- Governmental change - focus on housing and retro fit, MEES
- Cladding remediation
-defence work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is the role of a mediator in dispute resolution?

A

The mediator is a facilitator of the negotiations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

How would you go about appointing a mediator?

A

Through a nominating body such as the RICS dispute resolution service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Why is it necessary to- store documents / data for up to 15 years?

A

Firms may need information to respond to claims made against them. RICS Risk, liability and Insurance Practice infomation recommends that members retain their files for 15 years after providing any professional services,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Building saftey act What effect has there been on liability?

A

The building safety act increased the limitation period in the Defective Premises Act from 6 years to 15 years for new work and up to 30 years for retrospective works on dwellings.

a non-dwelling project limitation period will depend on the contract - under hand is 6 years and as a deed is 12 years.

there are grounds for extensions to this depending on when issues are identified. long-stop position of 15 years if the claimant did not know a loss was suffered earlier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Why is it important to maintain records of site notes?

A

Site notes provide a record of your on-site observations and can be useful as evidence in any negligence claim or complaint. they form a retrospective record of conduct and behaviour, and are prima facie evidence of the surveyor’s competence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What are the main principles of the GDPR Regulations as far as they affect your role? In what circumstances do you need to consider the requirements of the GDPR Regs?

A

During my role on behalf of my company I will sometimes act as a data processorfor the purposes of GDPR, for instance when working with clients, I will collect personal details from them such as addresses names and phone numbers as part of the project.

I need to be careful when personal data is shared with me that it is not accidentally shared with any other person and it is securely stored. One of the most common forms of data breach is human error – either sending emails by mistake to the wrong recipient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What are the limitations of using BCIS data?

A

BCIS data can be very high level, or there can be limited results for niche building types; for instance, I undertook a BRCA on a small airfield which had a control tower. There were only 2 or 3 analyses of air traffic control towers on the BCIS, and they were for large-scale airports, so they were not representative of the building I surveyed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

How do you use BCIS data and when would you use it?

A

I have typically used the BCIS when undertaking building reinstatement cost assessments and dilapidation schedules to inform the costs I input into them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is an EPC and what is it for?

A

An energy performance certificate aims to show how energy efficient a building is by giving it a rating and recommending some improvements that can be made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

When does an EPC have to be produced?

A

EPCs are needing on residential properties when they are sold or rented, and on commercial buildings when they are rented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What is the purpose of the MEES for commercial property?

A

to set a minimum efficiency standard of an E for new leases. to help encourage landlords to improve their premises.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Why was the Joint Statement on Moisture Movement produced? What does it say?

A

the joint statement aims to provide a standard methodgy that could be used to diagonse damp in buildings.

It focuses on looking at the issue in a hollstic manner and following the trail of evidence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

How would you diagnose sulphate attack in concrete? What would you see?

A

map cracking and swelling of concrete slabs caused by affected hardcore.

in mortar it will appear as horizontal cracking following the mortar beds. and can cause chimneys to lean.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

How would you diagnose cavity wall tie failure?

A

horizontal cracking at regular intervals, such as every 6 courses of brickwork. and potentially bowing of the wall, or roof movement.

Remedied cavity wall tie failure is often identifiable by patterns of patched bricks or render. if often similar properties have had cavity wall tie repairs done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What would you recommend as a remediation approach for sulphate attck and cavity wall tie failure ?

A

Sulphate attacks cannot be remedied and can be a structural risk. The contaminatnted materials must be removed and the slab or wall rebuilt.

Cavity wall tie failure can be remediated with retrofitted walls ties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

In your Gloucester hospital roof example, describe the roof build up? Where does the VCL go?

What typical flat roof form of construction / repair would you propose for a hospital flat roof with cable trays?

A

The build up was a warm deck roof made up of a plywood deck, then the VCL, then mineral wool insulation and a single ply membrane.

Due to the potential maintenance requirement, I would specify a covering that was suitable for access, such as a bitumen or GRP roof with rigid insulation suitable for the point loading of the cable trays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What do you understand by the term ‘load-paths’?

A

Load paths are the routes in which the weight of a structure is transferred to the ground; for instance, a lintel transfers the weight of the wall above to its bearing ends, and they transfer it downwards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

In your Bath housing defect survey, how did you eliminate other potential causes of cracking?

A

I looked at pervious engineers reports on the ground conditions and drainage which raised no issues.

I compared the cracking to typical cracking patterns. and looked at the direction of movement/ arrows of tension.

The cracking did not match the symptoms of subsidence (did not pass through the DPC) and it was consistent to all elevations of the property. two brick arches had previously been replaced, however the cracking had persisted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

How did you decide that vibration from the railway was the cause? What would you recommend in that situation?

A

The cracking did not match the symptoms of subsidence (did not pass through the DPC) and it was consistent to all elevations of the property. two brick arches had previously been replaced, however the cracking had persisted. so the movement was ongoing but was not progressive. it was also evident on the surrounding buildings.

I recommended the moratr joints be raked out and repointed in a flexible resin mortar to allow for continued movement but prevent water ingress and ongoing monitoring to check that the cracking remains stable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Merton College – 1 Hollywell Street – how does cement based mortar on soft clay bricks cause spalling?

A

Cement-based mortar sets very hard, as it is harder than soft brick. Water is retained in the brick and does not escape through the mortar joints. This leads to issues such as freeze-thaw damage, salt damage and erosion of the bricks, leaving the cement pointing behind.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

what sized holes would you expect for death watch beetles?

A

3-4mm

51
Q

What size holes do wood worm leave?

A

1.5mm

52
Q

5 Flaxfield Road – Describe what form of construction / build up you had and how you changed it.

A

The project was a single-storey extension that had originally been designed before the new part L requirements. The original concruction was for a block work and render cavity wall with 100mm mineral wool insulation to full fill. I took over the project as the changes came into force and I needed to find a better-performing insulation for the same cavity size. 90mm of PIR insulation met this requirement and allowed for a 10mm cavity.

53
Q

5 Flaxfield Road –What was the construction?

A

The original building was a semi-detched 1960’s council house of cavity wall construction. The extension was a single-storey blockwork cavity wall with a block and beam floor and a flat roof.

54
Q

Are there any potential issues in using PIR?

A
  • PIR is not a particularly sustaible material being derived from oil
  • being a rigid board they are harder to fit without gaps
55
Q

Rectors Lodge – what repairs were required for the various types of roof?

A

-There were some slipped stone slates to the pitched roof,

-the ashplate roof required some patch repairs to slumped upstands and cracks which I recommended be repaired in accordance with the mastic asphalt Council’s guidance.

  • The Copper roofing was in good condition and required no immediate repairs.
56
Q

Franks Lane – what did you need to consider when changing the underfloor heating from electric to wet system?

A

Wet systems require a deeper buildup than electric systems. To maintain the finished floor level, the floor screed would need to be reduced, or a step would be formed at the doorway.

57
Q

Rectors Lodge –What considerations did you make when recommending secondary glazing

A
  • reduced ventilation provided by leaky windows
  • can rot timber windows quicker
  • visual impact / statutory consent
    -may effect fire escape through windows if it reduces the opening size
58
Q

Please explain what understand from the terms: Liquidated damages

A

Liquid ascertained damages are the anticipated costs that the client would suffer if the contractor was late completing. A certificate of non-completion is required to claim LADs, and they must be provable loss.

59
Q

Please explain what understand from the terms: Site possession

A

Site possession is when the contractor is given a license to occupy the site and takes over responsibility for the site security, safety and insurance.

60
Q

Please explain what understand from the terms: Third party warrenties

A
  • mistake combining third party rights and collateral warrenties
  • Third-party rights a gives parties outside of the main contract the same rights to bring claims for breach of the contract.
  • collateral warranties provide a contractual link between parties outside of the main contract

Using collateral warranties rather than the default of third-party rights is preferable as the liability can be limited and controlled.

61
Q

Please explain what understand from the terms: Provisional sums

A

Psums are used in tenders to put a cost against undefined works. this can help to make tenders comparable as costs based on guess work could vary greatly.

62
Q

Please explain what understand from the terms: Rentention

A

Rentention is where a percentag of the contract sum is deducted from each valuation. the dectuted monies is then released at the end of the project, typically 2.5% at PC and 2.5% at end of defects. this acts as inducement to the contractor to finish the project snagging.

63
Q

Explain what you mean by a prolongation claim

A

A claim for costs associated with the extended programme. This could be as a loss and expense claim or as a variation

64
Q

What are the requirements under the contract for an extension of time – explain the process you would expect to follow.

A

Contractor to submit notice of likely delay
Contractor to submit claim of eot
CA to review if relevant event
CA to assess time claimed for in fair manner
Issue eot certificate extending the contract completion date

65
Q

What procedures are covered by a JCT IFC in relation to advance payments? How does this work?

A

An advanced payment can be used where there may be high upfront costs for the contractor such as materials or plant. under the JCT contract the contractor will need to provide a advanced payment bond and vesting certificate

An advanced payment bond can be used to protect the client from default by the contractor.

66
Q

Explain the process as CA for receipt, assessment and certification of an interim payment under JCT.

A

The contract will typically submit an application for payment; the CA will undertake a valuation of the works, including a site visit and make comments back on discrepancies with the application.

The CA then issues a payment certificate for the valuation minus previous valuations.

67
Q

How did you assess the value of works undertaken under a provisional sum.

A

we omitted all provisional sums at the start of the project. The contractor then provided a cost for undertaking the work which was reviewed and instructed as a variation when the cost was agreed.

68
Q

How do design risk assessments help to identify and mitigate risks to clients?

A

A design risk assessment makes sure that building are safe and easy to maintain when in use.

69
Q

What type of flooring did you specify for a kitchen environment? How did you determine its suitability?

A

I specd a Forbo flooring product that had a suitable non-slip rating (R11) but was not too heavily textured as this made cleaning the floor difficult and that was a key requirement for a kitchen environment.

70
Q

Bats – what legislation covers the protection and procedures for dealing with bats in buildings?

A

Wildlife and countryside act 1981

Conservation of habitats and species regulation 2017

71
Q

Explain the design solution that you implemented to be ‘bat-friendly’. Red brick house

A

Bats can get tangled in the fibres of breather membranes, which often results in their deaths. they therefore should not be used in buildings with bats. At the time of this project, there were no alternative membranes that could be used other than bitumen sarking felt. With agreement from the ecologist wood fibre sarking would mitigate the need for a breather membrane and the bats don’t get tangled in the fibers as the are too short.

72
Q

How did you calculate gutter size?

A

I didnot calculate the gutter sizes, i would ask a manufacturer or the roofing contractor to do this. On red brick house we were increasing the size of the existing gutters primarily for asethic reasons.

73
Q

Explain the use / purpose of the following and what they include / format: TDD

A

Techinical due dillgence surveys are typical used for pre-purchase of commercial property, they take the form of a custom written report that will focus on the main concerns of the client. but will cover the condition of the property, access arrangements, environmental concerns, planning issues and could include specialist comment on potential rental incomes

74
Q

Explain the use / purpose of the following and what they include / format: PPM

A

Planned preventative maintenance reports are tailored to the client’s needs, I have typically undertaken these on larger portfolios where we produce a photographic survey which identifies the maintenance requirements of the building over a set time period such as 10 years and puts cost data against each so maintenance budget planning

75
Q

Explain the use / purpose of the following and what they include / format: RCA

A

Reinstatement cost assessments are undertaken for insurance purposes they provide the likely rebuild cost should the building be total destroyed.

76
Q

What’s the difference between a condition survey and a schedule of condition?

A

A schedule of condition is a photograph record of the current condition of a building, it does not comment on defects or suggest redmies beyond recording their existence. This can be appended to a lease or be used as proof that damage was pre-existing in construction works.

A condition survey captures the current condition of a building and its defects, recommending remedial action.

77
Q

In addition to site maps, what else might you investigate in a desktop study for site history?

A

Planning history, listing entry if a heritage building, building control applications

78
Q

How would you assess the risk of encountering asbestos when undertaking inspection services?

A

Any building built pre-2000’s I would assume there’s likely to be ACMS present. For commercial buildings, I will request to see the asbestos register to help understand where asbestos is known.

79
Q

What are the risks associated with vermin faeces?

A

They can carry diseases and bacteria

80
Q

When might you recommend a thermal imaging survey? How would you commission one?

A

Thermal imaging can be useful to identfy various defects such as lack of airtightness, poor insulation installs, water ingress and electrical faults.

I would appoint an experienced thermal imaging surveyor to interpret the data correctly.

81
Q

What did the risk to the public relating to gravestones entail?

A

wobbly Gravestones could fall on members of the public causing death or injury. more than 8 people have been killed since 1979 by gravestones.

82
Q

Franks Lane – what was the floor construction? Why did you need to ventilate?

A

To prevent build-up of moisture and potential gas such as radon

83
Q

What procedures/guidance did you follow / is available for undertaking RCAs?

A

I used the RICS RCA Profesional standard guidance for cost assessments

84
Q

Brookbank Development – how did you come to the conclusion that the defects were caused by excessive thermal expansion?

A

the lead had split lines and had buckled,I suspect the lead was fixed along to much of its lenght

Other roofs had beeb retro fitted with neoprene gaskets

85
Q

What guidance would you refer to relating to workmanship with lead?

A

The lead sheet association/ lead sheet training academy handbook

86
Q

What do you understand the role of an expert witness to be?

A

In court cases, the judge and/or jury are not expected to understand complex technical details, so an expert witness provides the court with the technical explanation. Thye do not provide opinions only state the facts. Only expert witnesses can provide opinion evidence.

87
Q

How is the role of an expert witness important in bringing housing disrepair claims?

A

Expert witnesses can be important as they can help the jury understand why the defect has occurred and why it is unfit for habitation. They can also comment on hypothetical situations and recommend repairs and costs.

88
Q

Can you explain the role of the Building Regulations Principal Designer in relation to your role as a Building Surveyor?

A

Most building projects now require a BRPD, I need to ensure my clients are aware of the change in regulation and the need for a BRPD as many wont be.

89
Q

What process is involved in obtaining a Build Over Notice? What technical detail was involved?

A

An application and technical cross-section detail drawings must be submitted to the local water authority for their approval.

90
Q

What are the requirements for producing an Expert Witness report?

A
  • being impartial
  • being experienced and knowledgeable
  • the resource availability
    have the right PI

Junior staff should only produce reports under direct supervision or an experienced surveyor

91
Q

How is an Expert Witness appointed?

A

The solicitor will typically approach a surveyor to act as a expert witness for thier case.

92
Q

What goes into an Expert Witness report?

A

I understand that It would set out the technical facts of the case.

93
Q

What guidance is available to surveyors in acting as Expert Witness?

A

The RICS provide a certification scheme and a practice note.

94
Q

Crown Hotel – RCA – what would you take into account when considering ‘high quality’ when producing a BRCA report?

A

When collecting cost data from the BCIS I would use the upper Medien cost per m2.

95
Q

What goes into a Terminal Schedule of dilapidations?

A

a summary of the relevant leave clauses,
the endorsement
the schedule of breaches
the quantified demand

96
Q

What is the purpose of a terminal schedule of dilapidations?

A

The schedule is the landlords claim for costs against breaches of the lease which need to be rectified at the end of a tenacy

97
Q

When can a terminal schedule be produced / served?

A

Within a reasonable time at the end of the lease, The dilapidations protocol suggests this should be no later than 56 days after the end of the lease

98
Q

What did you look for specifically in the lease to assist in the preparation of the schedule? Terminal schedule of dilapidations

A

Yeilding up, decoration, repair, alteration clauses

99
Q

How did you advise the landlord relating to ambiguity in the lease clauses?

A

The lease did not clearly define whose responsibility it was to maintain the roof. I advised the client, who has a large property portfolio, that on future leases, they should ensure this is changed and to expect these costs to be challenged by the tenant.

100
Q

What guidance did you refer to when preparing the terminal schedule of dilapidations?

A

RICS dilapidations professional standard

101
Q

What legislation and legal guidance covers the dilapidations process?

A

The Landlord and tenant act 1954
The leasehold property (repairs) act 1938
The law of property act 1925

102
Q

How would you assess the compliance and performance of a door for fire safety purposes?

A

I can undertake a visual inspection of the fire door, however beyond that i would recommend a fire engineer be engaged.

103
Q

What standards apply to the performance of fire doors?

A

Fire doors typically come in FD30 or FD60

104
Q

What are the primary differences between Part B and BS9999 approach for assessing fire safety in commercial buildings?

A

BS9999 is a best practice document, but its approach to assessing the number of people that can occupy a building is calculated differently from Part B of the building regulations. BS9999 can be more flexible though in how you can achieve compliance through offsetting measures.

105
Q

Explain what preparation you would do before attending a site to conduct a progress and quality monitoring inspection.

A

-I would review the latest drawings, shedule of works and workmanship spesification
- I would review the programme
-I would research any specialist works such as CLT

106
Q

Why is works progress monitoring important in case of disputes arising?

A

quailty monitoring reports are a snapshot record of the works completed and ongoing n on site at a given time, if there was a dispute and it needed to be proven what was completed or not completed on programme these reports would provide documentation of that.

107
Q

In relation to works progress and quality monitoring, what is the difference between a contract administrator and Employer’s Agent role?

A

CA is for traditional contracts where, as EA is only for design and build contracts.

108
Q

What is the difference between ERs / CPs and a fully detailed specification?

A

ER’s are what the client wants to a achieve, CPs are how the contractor proposes to achieve the clients aims.

a detail specification is how a consultant would tell a contractor how to meet the client’s aims.

109
Q

What would you include in a works progress and quality monitoring report?

A
  • an overview of progress in the period
  • number od workers onsite
  • a review of the programme and progress against the programme
  • a review of design submittals
  • issues or queries to raise
110
Q

What do you understand by the term breathable construction.

A

Breathability refers to the ability of moisture to move through a building’s fabric. It is sometimes referred to as a ‘great coat’ building as opposed to a raincoat building. Rather than sealing a building to prevent water from getting in and out, you allow water vapour to come in and out.

111
Q

Explain the lime cycle

A

The lime cycle is the process of turning lime into quicklime, then slaked lime, which then sets back into limestone through carbonation.

112
Q

Why is it important to protect and record heritage buildings / assets.

A

They are a finite resource, a record of our history and they are a important part of the heritage and culture of the UK

113
Q

What is the purpose of a Heritage Impact Statement?

A

To assess if changes being made to the building and the level of harm, could be mitigated or are justifable

114
Q

What goes into a Heritage Impact Statement?

A

there should be a study done on the building to gauge the historical, architectural, and communal significance of the building. there should then be a impact assessment justifying the proposed changes and explaining the proposal.

115
Q

How did you assess the heritage impact from raising the roof level in order to increase insulation?

A

The building was grade II* listed. However, the significance of the building was due to its being built on medieval baby ruins, which were incorporated into the ground floor rooms. The roof, therefore, was only of lesser significance, and large areas of it had been altered in the 1900, meaning it had lost its original form. The benefit of making the property more energy efficient was therefore justifiable for the limited harm.

116
Q

What type of insulation did you specify? Red brick house

A

Ridif wood fibre sarking boards with a flexible woodfibre between the rafters.

117
Q

What considerations did you make when balancing the need for improved insulation with impact to the heritage asset?

A

The materials must be sympathetic and should have as little impact on original building fabric as possible. for instance if there are original lathe and plaster ceiling these should be left, but modern plasterboard ceilings could be replaced with breathable insulation and lime plaster finishes.

118
Q

On the doors at Merton College, what method of draughtproofing did you recommend to improve the thermal performance?

A

Rebated brush seals to the doors edge as these require only a small intervention to the fabric of the door and are not visible when the door is closed.

119
Q

How would you go about identifying who the project stakeholders would be?

A

At the inital meeting with the client I would discuss who will be using the building, and who they are representing.

120
Q

How would you identify and record project risks at the briefing stage of a project?

A

Through meeting and record them on a project risk register

121
Q

What information would you obtain and review to provide an overall master project programme? How would you review and update this during the project cycle?

A

I would discuss the client’s target completion date, and if it is feasible, I would work backwards from it; I would also establish any times that would not be possible for them, such as school terms.

I would look into the type of work that would be needed and anticipate how long the contract may need on site, for specialist works I might ask a contractor how long they would allow.

I would update the programme regularly before client meeting to show progress,

122
Q

When is PC?

A

There is no set definiation but typically when the client can take benifical occupation.

123
Q

What can PC tigger?

A
  • the start of the final account process
  • release of 50% retention monies
  • the client taking possession and control of the building
  • commencement of defects liability, rectification or maintenance period
  • cessation of any further liability for delay damages, whether liquidated or unliquidated
  • risk of loss or damage to the works passing to the client, terminating any further requirement for the contractor to insure and secure the works
  • the last milestone payment
  • obligations under third-party agreements, such as funding arrangements, bonds, guarantees, leases, sale agreements and so on
  • the contract administrator may not instruct the contractor to carry out variations after practical completion.
124
Q

when does the BSA apply?

A

all projects requiring building control approval

125
Q
A