Questions From Mocks Flashcards
How long was the actual planning period?
20 weeks in total
How long was allowed for planning period on the programme
16 weeks
What caused the lead valley to fail?
Thermal expansion over time and the bay lengths being overly long for the code of lead used caused cracking.
What code of lead did you specify for the valley?
Code 6 as per lead sheet training academy guidance
How did you assess the significance of the building?
The previously listed building consent pack had included an historic building assessment that had undertaken a study on the history of the property, which identified the areas of significance and how the building had evolved over time.
And the historic england guidance on conservation principles
How old is the farm house
18th century
What is the maximum escape distance in one direction that required the second staircase.
It depends on the use of the building, the distances are set out in approved document B.
For this building In a single direction the maximum distance is 18m.
This is increased to 45m if there is two directions of escape.
What would you tella client if they asked you to look at the suitability of fire doors
I can undertake a visual inspection only, a fire engineer would need to assess suitability.
What are the method statement for asesbestos removal at overford
Negative pressure enclosure, air quality monitoring, under licence work
What are the client duties under CDM
Apoint a principle designer and contractors
The pd usally takes on the following client duties
Provide the PCI information.
Ensuring suitable management arrangements are made for the project
Notifying the hse were required
Ensure the project jas sufficient time and resources
Check the cpp
Maintain the h&s file
What does the lead designer do
Coordinate the design team
How did you assess quaily of work
I compared the work onsite to the spesification and schedule of work
What is Ridges complaint handling procedure.
A complaint should be ackonwledged as soon as possible and the CHP provided
If a complaint has been made verbally this must then be provided in a written form.
The complaint will be responded by a partner within 14 days, the outcome will then be decided within 28 days from any further comment.
If not satisfactory the complaint will be reviewed afresh by the responible senior partner within 28 days.
What is the width of a door for a wheelchair to pass through
It can be as little as 750mm but it depends on situation, Ideally 1m width. Approved document M has a table which sets out requirements.
How long from the end of a tenancy does the landlord have to bring a claim
schedules should be sent within 56 days after end of the lease
What is the difference between a named or nominated subcontractor?
named subcontractors are chosen from a listed, nominated are selected directly
What ate some protected characteristics
Race, sexual orientation, religion, age
What certificates would you issue at the end of the project.
Pc certificate then certificate of making good at the end of the defect period
What would you need for an advanced payment under the JCT
An advanced payment bond and a vesting certificate for any materials bought in advance kept off site
How would you advise on remedying defects out of scope (Fifield)
I could give high-level general advice, but generally I would avoid giving detailed advice on items outside of the scope of services.
What H&S regulation do you need to be aware of when working in roofs?
the health and safety at Work Act, and the working at height regulations
Did the asbestos removal company certificate certify that there were absolutely no fibres in the air?
a certificate of reoccupation was issued which assess that the air quality was within tolerance
what effect does MEES have
Buildings with a rating of E or below cannot be let without an exemption
what are LADS
LADS are the damages a contractor pays for being in breach of contract
what are the different levels of fire protection
Category L1: This is the most comprehensive level of protection, with detectors in every area of the building that are linked to a centralized alarm system.
Category L2: This system provides early warning of a fire in another room, with alarms in high-risk rooms and near escape routes.
Category L3: This system provides early warning to everyone, with detectors in all rooms and escape routes.
Category L4: This system has manual call points and automatic fire detection along escape routes.
Category M: This is the standard type of fire alarm system, where staff manually activate the alarm when they discover a fire.
Why do want to be part of the RICS
It lets clients know that i am working with a high standard and will be following a clear ethical framework
It allows me to continue my career development and learning
What are the main changes the the jct 2024
Gender neutral language
Notices by email
Interim eot reveiw time reduced to 8 weeks
Employer must ask for further information on notification of delay in 14 days
Pandemics added to relevent events but not relevant matters
Environmental, collaborative working and early notification of disputes Optional provisiond now made mandatory
When do you need to notify the HSE of a construction project
Over 30 days and more than 20 worker at any one times
or
500 worker days
How do you notify the HSE of a notable project?
it is the client’s duty to submit a F10 form
Under CDM, what must be provided to the client upon completion?
The Health and safety file
Why would you choose an intermediate form of contract over Minor works?
Ability to name sub-contractors rather than just nominate, advanced payments.
What did you do in the value engineering exercise
Review the existing scope of works for where changes could be made to provide the client with better value, such as by replacing hardwood engineered flooring with quality carpets.
name the three types of asbestos
Blue - Crocidolite - most dangerous
Brown - Amosite
white - Chrysotile - least dangerous
What is the regulation relating to asbestos work?
Control of asbestos regulations 2012
What work was outstanding that led to a non-completion certificate?
There were external drainage works, commissioning of the heating system, and external decorations still to be undertaken.
What are the time scales for LBC?
LBC lasts for three years; the determination period should be 8 weeks but is often 16 weeks or more.
When the contractor was appointed in June, was this entering into a contract or tender award?
This appoint to informed the contractor that the client intented to award the contractor to them.
What do you do if you receive a complaint?
Acknowledge receipt of the complaint and pass it to the manager in charge of complaints handling
What are the benefits of email use?
Emails are a quick way to get written confirmation, however they have limitations and can lead to miscommunication.
What is the difference between mediation and negotiation?
Mediation, there is a third party who facilitates the agreement process
negotiation is just between the two parties
What do you do to stop disputes arising in projects?
*Pratice good managment - project, contractor, team and client
*clear contract documents
*record keeping
*good payment practices
*clear and regular communication
What are some upgrades that can be recommended on a EPC?
Cavity wall insulation or PV panels
What are the main types of dampess?
Penetrating damp, condensation and rising damp
How would you identify dry rot?
Orange spore dust, large spongey fruiting body, cuboidal cracking to timber
How would you identify wet rot?
spongy crumbling timber, fruiting body growing on the timber, musty smell
how would you assess structural crack sizes?
The BRE provides a table categorising cracking
0 - Hairline cracks: Less than 0.1 mm in width. No repair action required.
1 - Fine cracks: Up to 1 mm in width. Generally restricted to internal wall finishes. Easily treated using normal decoration.
2 - Cracks easily filled: Up to 5 mm in width. Not necessarily visible externally, but doors and windows may require adjusting to prevent sticking. Can be masked by suitable linings.
3 - Cracks that require opening up: Widths of 5-15 mm. Weather-tightness and service pipes may be affected. External brickwork may need repointing or, in some cases, to be replaced.
4 - Extensive damage: Widths of 15-25 mm. Windows and door frames become distorted, walls lean or bulge noticeably. Requires breaking-out and replacement of wall sections.
5 – Structural damage: Widths greater than 25 mm. Beams lose their bearing, walls require shoring, and the structure is generally unstable. May require major repair works.
why does cement pointing damage soft bricks?
Cement pointing doesn’t allow moisture to breathe out of the bricks, which can lead to frost damage and salt crystal growth
Cement pointing is incompatible with the soft, flexible mortar behind it, which can cause it to crack and fail.