Time IOT&T Flashcards
What are the KEY Outputs to the Define Activities (Planning) (2)?
Activity Plan
Activity Attributes
What are the KEY Tools & Techniques for Define Activities (Planning) (2)?
Decomposition
Rolling Wave Planning
What are the KEY Tools & Techniques to Sequence Activities (Planning) (3)?
Precedence Diagramming Method (PDM)
Dependency Determination
Leads and Lags
What is the KEY Output to Sequence Activities (Planning) (1)?
Project Schedule Network Diagrams
What are the KEY Tools & Techniques to Estimate Activity Resources (Planning) (3)?
Alternative Analysis
Published Estimating Data
Bottom-up Estimating
What are the KEY Outputs to Estimate Activity Resources (Planning) (2)?
Activity Resource Requirements
Resource Breakdown Structure
What are the KEY Tools & Techniques for Estimate Activity Durations (Planning) (3)?
Analogous Estimating (top down estimating) Parametric Estimating Three-Point Estimating
What is the KEY Outputs to Estimate Activity Durations (Planning) (1)?
Activity Duration Estimates
What are the KEY Tools and Techniques to Develop Schedule (Planning) (5)?
Critical Path Method Critical Chain Method Resource Optimization Techniques Modeling Techniques Schedule Compression
What is the KEY Output to Develop Schedule (Planning) (1)?
Schedule Baseline
What is the Key Input to Control Schedule (Monitory & Control) (1)?
Work Performance Data
What is the KEY Output to Control Schedule (Monitor & Control) (1)?
Work Performance Information
Change Requests