Cost Management Flashcards
The most important output of the Plan Cost Management process is the:
Cost Management Plan
Which process provides direction on how the project costs will be managed throughout the project?
Plan Cost Management
What is another name for Analogous Estimating?
Top-Down Estimating
__________ ___________ involves using the actual costs of previous, similar project to estimate the cost of the current project. it is a gross value approach which is often used at the beginning of a project when there is little specific detail?
Analogous Estimating
Parametric Estimating involves using a ________ ________ between historical data and other variables in UNIT VALUE form to calculate cost estimates. Sine in previous similar projects, it took $100 to develop each web page, we estimate that 4,000 pages will cost $400,000.
Statistical Relationship
Bottom-up Estimating involves estimating the cost of individual work packages or individual schedule __________ with the greatest level of specific detail. Detailed cost is then summarized or “rolled-up” to higher levels for subsequent reporting and tracking purposes.
Activities
Three-Point Estimating can be used to improve the accuracy of ______ ______ _______ by using three values (______, _________, ________ ________), instead of one to account for estimating uncertainty.
Activity Cost Estimates; Pessimistic; Optimistic; Most Likely
What is Reserve Analysis?
Where established appropriate cost reserves for unknown situations. Two types of reserves may be considered: Contingency Reserves and Management Reserves
_______ _______ ________ involves asking vendors to submit bids for project, or certain portions of it. We plan to buy 20 computers to work on the web pages, so the bids received from the vendors help us to develop a more realistic cost estimate for the project.
Vendor Bid Analysis
What is the accuracy for a Rough Order of Magnitude (ROM) estimate?
-25% to +75%
What is the accuracy for a Budget estimate?
-10% to +25%
What is Cost of Quality?
It involves determining the costs associated with conforming to the quality requirements of the project.
What is the accuracy for a Definitive estimate?
-5% to +10%
The Estimate Costs process should be performed in parallel with which Time Process?
Estimate Activity Resources
How are costs estimates derived with bottom-up estimating?
Estimates from Work Packages or activities are rolled up or summarized at higher levels.