Cost IOT&T Flashcards

0
Q

What is the KEY Tool & Technique for Estimate Costs (Planning) (1)?

A

Cost of Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are the KEY Inputs to Estimate Costs (Planning) (2)?

A

Scope Baseline

Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the KEY Output to Estimate Costs (Planning) (1)?

A

Activity Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the KEY Tool & Technique for Determine Budget (Planning) (3)?

A

Cost Aggregation
Reserve Analysis
Funding Limit Reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the KEY Output for Determine Budget (Planning) (1)?

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the KEY Input to Control Costs (Monitor & Control) (1)?

A

Work Performance Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the KEY Tools & Techniques for Control Costs (Monitor & Control) (2)?

A

Earned Value Management

Forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the KEY Output for Control Costs (Monitor & Control) (1)?

A

Work Performance Information