PMP Math Flashcards
What is the formula for Schedule Variance (SV)? And what knowledge area does it apply?
EV-PV (an answer greater than one is good) - Cost Management
What is the formula for Three Point Estimating and what knowledge area does it apply?
Pessimistic Optimistic Most Likely Formula P+O(ML*4)/6 TIME MANAGEMENT
What is the formula for Cost Variance (CV) and what knowledge area does it apply?
EV-AC (an answer greater than 1 is good) - Cost Management
What is the formula for Schedule Performance Index (SPI) and what knowledge area does it apply?
EV / PV (an answer greater than 1 is good) Cost Management
What is the formula for Cost Performance Index (CPI) and what knowledge area does it apply?
EV / AC (an answer greater than one is good) Cost Management
What is the formula for Percent Complete, and what knowledge area does it apply?
EV / BAC x 100 - Cost Management
What is the formula for Estimate @ Completion (EAC - Typical)?
BAC / CPI
What is the formula for Estimate 2 Complete (ETC)
EAC - AC
What is the formula for Variance @ Completion (VAC)?
BAC - EAC
What is the formula for To Complete Performance Index (TCPI) based on BAC?
(BAC - EV) / (BAC-AC)
What is the formula for To Complete Performance Index (TCPI) based on EAC?
(BAC - EV) / (EAC - AC)