What is the formula for Schedule Variance (SV)? And what knowledge area does it apply?

A

EV-PV (an answer greater than one is good) - Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What is the formula for Three Point Estimating and what knowledge area does it apply?

A
Pessimistic
Optimistic
Most Likely
Formula P+O(ML*4)/6
TIME MANAGEMENT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula for Cost Variance (CV) and what knowledge area does it apply?

A

EV-AC (an answer greater than 1 is good) - Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the formula for Schedule Performance Index (SPI) and what knowledge area does it apply?

A

EV / PV (an answer greater than 1 is good) Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the formula for Cost Performance Index (CPI) and what knowledge area does it apply?

A

EV / AC (an answer greater than one is good) Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the formula for Percent Complete, and what knowledge area does it apply?

A

EV / BAC x 100 - Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for Estimate @ Completion (EAC - Typical)?

A

BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for Estimate 2 Complete (ETC)

A

EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the formula for Variance @ Completion (VAC)?

A

BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the formula for To Complete Performance Index (TCPI) based on BAC?

A

(BAC - EV) / (BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the formula for To Complete Performance Index (TCPI) based on EAC?

A

(BAC - EV) / (EAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly