Scope IOT&T Flashcards
What is the KEY Tool & Technique for Plan Scope Management (Planning) (1)?
Expert Judgement
What are the KEY Inputs to Plan Scope Management (Planning) (1)?
Project Charter
PMP, EEF, OPA are others
What is the KEY Output of Plan Scope Management (Planning) (1)?
Requirements Management Plan (RMP)
Scope Management Plan
What are the KEY Tools & Techniques for Collect Requirements (Planning) (5)?
Focus Groups Facilitated Workshops Group creativity techniques Group Discussion Making Techniques Prototypes
What are the KEY Outputs to Collect Requirements (Planning) (2)?
Requirements documentation
Requirements traceability matrix
What is the KEY Output to Define Scope (Planning) (1)?
Project Scope Statement
What is the KEY Tool & Techniques for Create WBS (Planning) (1)?
Decomposition
What is the KEY Output to Create WBS (Planning) (1)?
Scope Baseline
(Creating the WBS is defined as “Decomposition” tools & techniques a practice that focuses the team (team building exercise) the output being the scope baseline.
What is the KEY Input to Validate Scope (Monitor & Control) (1)?
Verified deliverables
PMP, Requirements Doc, Traceability matrix, work performance data
What is the KEY Tool & Technique for Validate Scope (Monitor & Control) (1)?
Inspection
Group decision-making techniques
What is the KEY Output for Validate Scope (Monitor & Control) (1)?
Accepted deliverables
What is the KEY Input to Control Scope (Monitor & Control) (1)?
Work Performance Data
What is the KEY Tool & Technique for Control Scope (Monitor & Control) (1)?
Variance analysis
What is the KEY Output to Control Scope (Monitor & Control) (1)?
Work Performance Data